Solar, wind and battery projects near Nottingham (NG13)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG13 (Rushcliffe): 10 approved but not yet running, 5 operational. The largest live scheme is Longhedge Solar Farm (49.9 MW solar farm, approved on 23 October 2024, not yet built), 5.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NG13
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Elton solar farmsolar farm | solar farm | 5 | operationalupdated Mar 2016 | Aug 2014 | granted Feb 2015 | Mar 2016 | Rushcliffe | 4.1 |
| Longhedge Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Dec 2022 | refused Mar 2023 | Feb 2026 | Rushcliffe | 5.2 |
| Jericho Covert Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Nov 2023 | Oct 2020 | granted Aug 2022 | Nov 2023 | Melton | 5.3 |
| Lodge Farm - Orstonsolar farm | solar farm | 12.4 | operationalupdated May 2014 | Aug 2013 | granted Nov 2013 | May 2014 | Rushcliffe | 5.4 |
| Langar Lanesolar farm | solar farm | 10 | operationalupdated Dec 2017 | Aug 2014 | granted Dec 2014 | Dec 2017 | Rushcliffe | 5.9 |
| Heron Solar Farm & Battery Storagesolar farm | solar farm | 20 | approved, not builtupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | Rushcliffe | 8.0 |
| Heron Solar Farm & Battery Storagebattery storage | battery storage | 20 | approved, not builtupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | Rushcliffe | 8.0 |
| Stoke Bardolph Farmwind farm | wind farm | 3.4 | refusedupdated May 2012 | Apr 2010 | refused Apr 2012 | May 2012 | Gedling | 9.5 |
| Severn Trent Water - Stoke Bardolph Wind Turbinewind turbine | wind turbine | 1.5 | operationalupdated Dec 2015 | Dec 2012 | granted Sep 2013 | Dec 2015 | Gedling | 9.5 |
| Stragglethorpe Road farmsolar farm | solar farm | 5 | operationalupdated Aug 2016 | Jan 2015 | granted Dec 2015 | Aug 2016 | Rushcliffe | 9.9 |
| Cotgrave Solar Farm Batterybattery storage | battery storage | 1 | abandonedupdated Mar 2019 | Dec 2015 | — | Mar 2019 | Rushcliffe | 9.9 |
| Sewstern Lane Wind Farmwind farm | wind farm | 15 | refusedupdated Nov 2015 | Apr 2015 | refused Oct 2015 | Nov 2015 | South Kesteven | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| New Lane, Whattonsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Dec 2021 | Dec 2021 | granted Feb 2022 | Dec 2021 | Rushcliffe | 0.3 |
| Smite Lane Farm, Thorotonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2022 | Jul 2022 | granted Sep 2022 | Sep 2022 | Rushcliffe | 3.1 |
| Orston Shooting Ground, Bottesford Lanebattery storage | battery storage | 0.4 | approved, not builtupdated Mar 2026 | Mar 2025 | granted Feb 2026 | Mar 2026 | Newark and Sherwood | 6.4 |
| Orston Shooting Ground, Bottesford Lanesolar farm | solar farm | 0.2 | approved, not builtupdated Mar 2026 | Mar 2025 | granted Feb 2026 | Mar 2026 | Newark and Sherwood | 6.4 |
| Belvoir Fruit Farms, Barkestone Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Melton | 6.7 |
| Hangar, Roseland Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted Apr 2026 | Jun 2026 | South Kesteven | 9.3 |
Distance from the average position of the NG13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 0 | 5 | 4 | 0 | 120 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.7 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 3 | 0 | 2 | 0 | 0 | 20.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Rushcliffe decides solar, wind and battery applications
| Applications | Rushcliffe | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 4 of 34 | 12% |
| Battery storage refused | 3 of 9 | 16% |
| Median time from submission to decision | 23.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG13, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.