Energy Projects Near You

Longhedge Solar Farm (49.9 MW)

Longhedge Solar Farm is a 49.9 MW solar farm project in Rushcliffe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 October 2024, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Rushcliffecouncil area

Planning timeline

DateStage
2 December 2022Application submitted
30 March 2023Refused by the planning authority
23 October 2024Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Renewable Energy Systems
Planning authority
Rushcliffe
Planning application reference
22/02241/FUL
Site area
94.2 ha
Address (REPD)
Longhedge Solar Farm Shelton Road Thoroton
Council area (by location)
Rushcliffe
Time to decision
17 weeks
Contracts for Difference
AR7a
REPD reference
11063

Who decides

ApplicationsRushcliffeUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused4 of 3412%
Battery storage refused3 of 916%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lodge Farm - Orstonsolar farm12.4operational2.2
Elton solar farmsolar farm5operational3.7
Fox Covert Wind Farmwind farm10refused6.1
Thackson's Well Wind Farmwind farm23refused6.3
Sewstern Lane Wind Farmwind farm15refused6.6
Jericho Covert Solar Farmsolar farm49.9approved, not built7.1
Hawton Wind Farmwind farm9operational7.8
The Grangesolar farm49.9operational7.9
Bypass Solar Farmsolar farm50approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9816, -0.8522).