Energy Projects Near You

Bypass Solar Farm (50 MW)

Bypass Solar Farm is a 50 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 March 2021, not yet built; the record was last updated on 21 May 2021. REPD also records that the planning permission expired on 1 March 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtmay be out of datestatus in REPD
21 May 2021record last updated
South Kestevencouncil area

REPD also records that the planning permission expired on 1 March 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
24 August 2020Application submitted
1 March 2021Planning permission granted
1 March 2024Permission expired

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
21 May 2021
Operator or applicant
By-Pass Farm Solar Limited
Planning authority
South Kesteven
Planning application reference
S20/1433
Site area
85.2 ha
Address (REPD)
S/O The A1, Foston By-Pass, Foston, Grantham
Council area (by location)
South Kesteven
Time to decision
27 weeks
REPD reference
9050

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grantham Solar Farmsolar farm5operational0.8
Thackson's Well Wind Farmwind farm23refused1.7
Sewstern Lane Wind Farmwind farm15refused2.3
Pastures Farm solar park (Gonerby Lane)solar farm5permission expired3.7
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational4.5
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built4.6
Copley Farmsolar farm30operational5.5
Copley Farmsolar farm10.1abandoned5.5
Temple Hill Wind Farmwind farm15refused6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9725, -0.735).