Copley Farm (10.1 MW solar farm)

Copley Farm is a 10.1 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 26 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.1 MWsolar farm
abandonedstatus in REPD
26 January 2016record last updated
South Kestevencouncil area

Planning timeline

DateStage
8 August 2014Application submitted
3 December 2014Planning permission granted
3 December 2017Permission expired

Project details

Technology
solar farm
Capacity
10.1 MW
Status (REPD)
abandoned
Record last updated
26 January 2016
Operator or applicant
TGC Renewables
Planning authority
South Kesteven
Planning application reference
S14/2290
Site area
12.0 ha
Address (REPD)
Doddington Lane, Claypole, Newark
Council area (by location)
South Kesteven
Time to decision
17 weeks
REPD reference
2246

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Copley Farmsolar farm30operational<0.1
Temple Hill Wind Farmwind farm15refused4.6
Bypass Solar Farmsolar farm50approved, not built5.5
Fulbeck Airfield Wind Farmwind farm25refused5.7
Grantham Solar Farmsolar farm5operational5.7
Fox Covert Wind Farmwind farm10refused6.0
Thackson's Well Wind Farmwind farm23refused6.0
Hawton Wind Farmwind farm9operational6.0
The Grangesolar farm49.9operational6.7