Grantham Solar Farm (5 MW)

Grantham Solar Farm is a 5 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 16 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 March 2016record last updated
South Kestevencouncil area

Planning timeline

DateStage
2 April 2015Application submitted
24 June 2015Planning permission granted
1 October 2015Construction started
15 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 March 2016
Operator or applicant
British Solar Renewables
Planning authority
South Kesteven
Planning application reference
S15/0383
Address (REPD)
Land south-east of Pasture Far, Allington Lane, Foston, Grantham
Council area (by location)
South Kesteven
Time to decision
12 weeks
REPD reference
5149

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bypass Solar Farmsolar farm50approved, not built0.8
Thackson's Well Wind Farmwind farm23refused2.5
Sewstern Lane Wind Farmwind farm15refused2.9
Pastures Farm solar park (Gonerby Lane)solar farm5permission expired3.0
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational3.6
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built3.8
Copley Farmsolar farm30operational5.7
Copley Farmsolar farm10.1abandoned5.7
Temple Hill Wind Farmwind farm15refused5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9712, -0.7225).