Energy Projects Near You

Renewable energy projects in South Kesteven

44 solar, wind or battery projects of 150 kW or more are located in South Kesteven (REPD, July 2026 extract): 3 pending, 23 approved but not running, 6 operational and 8 refused. The council refused 14 of 40 decided applications (35%; UK 19%), with a median 15 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44projects in the council area
3awaiting a decision
23approved, not running
35%of decisions refused

How South Kesteven decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Projects in South Kesteven

Projects of 1 MW and more (29)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Canners Lane Energy Park, High Dikebattery storagebattery storage1,000application submittedupdated Oct 2025Sep 2025—Oct 2025
Gonerby Moor, Great Gonerby Solar Farmsolar farmsolar farm60operationalupdated Jul 2026May 2021granted Nov 2021Jul 2026
Bypass Solar Farmsolar farmsolar farm50approved, not built may be out of dateupdated May 2021Aug 2020granted Mar 2021May 2021
Ash Tree Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026
Solar Farm at Welby Solar Farmsolar farmsolar farm46approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025
Glebe Farm Solar Farmsolar farmsolar farm38.8refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025
Copley Farmsolar farmsolar farm30operationalupdated Mar 2016Jan 2014granted Jan 2015Mar 2016
Home Farm Solar PV Farmsolar farmsolar farm28approved, not builtupdated Mar 2025Dec 2024granted Mar 2025Mar 2025
Washdyke Farm, Billingborough Road Solar farmsolar farmsolar farm27approved, not builtupdated Feb 2026Mar 2023granted Apr 2024Feb 2026
Manor Farmbattery storagebattery storage26permission expiredupdated Mar 2023Jan 2019granted May 2019Mar 2023
Fulbeck Airfield Wind Farmwind farmwind farm25refusedupdated Apr 2017Aug 2015refused Mar 2017Apr 2017
Ash Tree Solar Farm & Battery Storagebattery storagebattery storage25approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026
Side Barn, Church Lane Solar Farmsolar farmsolar farm24approved, not builtupdated Jan 2025Apr 2024granted Jan 2025Jan 2025
Thackson's Well Wind Farmwind farmwind farm23refusedupdated Nov 2008Nov 2007refused Mar 2008Nov 2008
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farmsolar farm23approved, not builtupdated Jul 2025Oct 2023granted Jan 2024Jul 2025
Limes Farm Solar Farm & Battery Energy Storagesolar farmsolar farm20approved, not builtupdated May 2025Feb 2025granted May 2025May 2025
Highfield Farmsolar farmsolar farm17refusedupdated Jul 2014Mar 2014refused Jun 2014Jul 2014
Temple Hill Wind Farmwind farmwind farm15refusedupdated Mar 2015Oct 2013refused Mar 2015Mar 2015
Sewstern Lane Wind Farmwind farmwind farm15refusedupdated Nov 2015Apr 2015refused Oct 2015Nov 2015
Northorpe Fen Farm, Fen Road Solar Farmsolar farmsolar farm15approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026
Deeping Gate Tree Nurseries solar parksolar farmsolar farm13refusedupdated Jan 2014Aug 2013refused Dec 2013Jan 2014
Neslam Wind Farmwind farmwind farm12application withdrawnupdated Nov 2010Feb 2009—Nov 2010
Copley Farmsolar farmsolar farm10.1abandonedupdated Jan 2016Aug 2014granted Dec 2014Jan 2016
Pastures Farm solar park (Gonerby Lane)solar farmsolar farm5permission expiredupdated Mar 2018Feb 2015granted Jun 2015Mar 2018
Grantham Solar Farmsolar farmsolar farm5operationalupdated Mar 2016Apr 2015granted Jun 2015Mar 2016
High Dyke (Mill Farm)solar farmsolar farm5operationalupdated Jan 2017Aug 2015granted Nov 2015Jan 2017
Heath Lanesolar farmsolar farm5refusedupdated Nov 2015Sep 2015refused Mar 2016Nov 2015
Marston Solar Farmsolar farmsolar farm4.9operationalupdated Aug 2011Mar 2011granted May 2011Aug 2011
Limes Farm Solar Farmsolar farmsolar farm4.6operationalupdated Apr 2013Feb 2011granted Apr 2011Apr 2013
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Mid UK Recycling, Caythorpe Heath Lanerooftop solarrooftop solar1approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
Morrisonrooftop solarrooftop solar0.7approved, not builtupdated Apr 2022Mar 2022granted Jun 2022Apr 2022
MV Fruehauf Limited, Houghton Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2025Mar 2025granted May 2025May 2025
Openfield, Colsterworthrooftop solarrooftop solar0.4approved, not builtupdated Jul 2022Jun 2022granted Aug 2022Jul 2022
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024
Hangar, Roseland Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Nov 2025granted Apr 2026Jun 2026
Walton Girls School, Kitty Briggs Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
BGB Engineering Limited Solar Panels Schemerooftop solarrooftop solar0.2approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024
Belton Garden Centre, Grantham Road Solar Arraysrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023
Cherryholt Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022
Kellington House, South Fen Roadrooftop solarrooftop solar0.1approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023
Limes Farm Solar Farm & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated May 2025Feb 2025granted May 2025May 2025
Gonerby Moorbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023
Welby Solar Farm, Welbybattery storagebattery storage—approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025

Postcode districts in South Kesteven

DistrictProjects within 10 kmPendingApprovedOperational
NG31283154
NG32322165
NG333111
PE912062
PE106051

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to South Kesteven by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.