Side Barn, Church Lane Solar Farm (24 MW)

Side Barn, Church Lane Solar Farm is a 24 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 January 2025, not yet built; the record was last updated on 27 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
approved, not builtstatus in REPD
27 January 2025record last updated
South Kestevencouncil area

Planning timeline

DateStage
4 April 2024Application submitted
25 July 2024Refused by the planning authority
16 August 2024Appeal lodged
15 January 2025Planning permission granted
15 January 2025Appeal allowed
15 January 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
27 January 2025
Operator or applicant
PS Renewables Limited
Planning authority
South Kesteven
Planning application reference
S24/0360
Appeal reference
APP/E2530/W/24/3350191
Site area
42.4 ha
Address (REPD)
Side Barn Church Lane
Council area (by location)
South Kesteven
Time to decision
41 weeks
Name in REPD
Side Barn, Church Lane - Solar Farm
REPD reference
13592

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Welby Solar Farmsolar farm46approved, not built0.2
Glebe Farm Solar Farmsolar farm38.8refused1.7
Manor Farmbattery storage26permission expired2.5
Ash Tree Solar Farm & Battery Storagesolar farm49.9approved, not built3.1
Heath Lanesolar farm5refused5.3
High Dyke (Mill Farm)solar farm5operational6.4
Highfield Farmsolar farm17refused7.9
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational8.7
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9315, -0.5503).