Solar, wind and battery projects near Grantham (NG32)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG32 (South Kesteven): 2 are waiting for a planning decision, 16 approved but not yet running, 5 operational. The largest live scheme is Bypass Solar Farm (50 MW solar farm, approved on 1 March 2021, not yet built; REPD status may be out of date), 6.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
2awaiting a decision
16approved, not running
5operational

Projects within 10 km of NG32

Projects of 1 MW and more (21)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gonerby Moor, Great Gonerby Solar Farmsolar farmsolar farm60operationalupdated Jul 2026May 2021granted Nov 2021Jul 2026South Kesteven1.6
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farmsolar farm23approved, not builtupdated Jul 2025Oct 2023granted Jan 2024Jul 2025South Kesteven1.9
Pastures Farm solar park (Gonerby Lane)solar farmsolar farm5permission expiredupdated Mar 2018Feb 2015granted Jun 2015Mar 2018South Kesteven3.2
Marston Solar Farmsolar farmsolar farm4.9operationalupdated Aug 2011Mar 2011granted May 2011Aug 2011South Kesteven3.3
Manor Farmbattery storagebattery storage26permission expiredupdated Mar 2023Jan 2019granted May 2019Mar 2023South Kesteven5.1
Grantham Solar Farmsolar farmsolar farm5operationalupdated Mar 2016Apr 2015granted Jun 2015Mar 2016South Kesteven5.3
Heath Lanesolar farmsolar farm5refusedupdated Nov 2015Sep 2015refused Mar 2016Nov 2015South Kesteven5.6
Bypass Solar Farmsolar farmsolar farm50approved, not built may be out of dateupdated May 2021Aug 2020granted Mar 2021May 2021South Kesteven6.1
Highfield Farmsolar farmsolar farm17refusedupdated Jul 2014Mar 2014refused Jun 2014Jul 2014South Kesteven6.1
Ash Tree Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Kesteven6.4
Ash Tree Solar Farm & Battery Storagebattery storagebattery storage25approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Kesteven6.4
Glebe Farm Solar Farmsolar farmsolar farm38.8refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025South Kesteven6.9
Temple Hill Wind Farmwind farmwind farm15refusedupdated Mar 2015Oct 2013refused Mar 2015Mar 2015South Kesteven7.1
Side Barn, Church Lane Solar Farmsolar farmsolar farm24approved, not builtupdated Jan 2025Apr 2024granted Jan 2025Jan 2025South Kesteven7.1
Solar Farm at Welby Solar Farmsolar farmsolar farm46approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025South Kesteven7.1
New Earth Solutions West, High Dike Solar Panels & Battery Sroragesolar farmsolar farm4.8approved, not built may be out of dateupdated Jun 2023Nov 2022granted Jan 2023Jun 2023North Kesteven7.2
Sewstern Lane Wind Farmwind farmwind farm15refusedupdated Nov 2015Apr 2015refused Oct 2015Nov 2015South Kesteven7.4
Thackson's Well Wind Farmwind farmwind farm23refusedupdated Nov 2008Nov 2007refused Mar 2008Nov 2008South Kesteven7.6
High Dyke (Mill Farm)solar farmsolar farm5operationalupdated Jan 2017Aug 2015granted Nov 2015Jan 2017South Kesteven8.4
Copley Farmsolar farmsolar farm30operationalupdated Mar 2016Jan 2014granted Jan 2015Mar 2016South Kesteven9.7
Copley Farmsolar farmsolar farm10.1abandonedupdated Jan 2016Aug 2014granted Dec 2014Jan 2016South Kesteven9.7
Smaller schemes under 1 MW, mostly rooftop solar (11)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Belton Garden Centre, Grantham Road Solar Arraysrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023South Kesteven1.8
Gonerby Moorbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023South Kesteven3.2
BGB Engineering Limited Solar Panels Schemerooftop solarrooftop solar0.2approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022South Kesteven4.9
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024South Kesteven5.0
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024South Kesteven5.0
MV Fruehauf Limited, Houghton Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2025Mar 2025granted May 2025May 2025South Kesteven5.6
Walton Girls School, Kitty Briggs Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025South Kesteven6.0
Welby Solar Farm, Welbybattery storagebattery storage—approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025South Kesteven7.1
New Earth Solutions West, High Dike Solar Panels & Battery Sroragebattery storagebattery storage—approved, not built may be out of dateupdated Jun 2023Nov 2022granted Jan 2023Jun 2023North Kesteven7.2
Hangar, Roseland Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Nov 2025granted Apr 2026Jun 2026South Kesteven8.5
Mid UK Recycling, Caythorpe Heath Lanerooftop solarrooftop solar1approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022South Kesteven9.2

Distance from the average position of the NG32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm160653198
Rooftop solar826002.7
Wind farm300030
Battery storage5040025

MW in pipeline: pending, approved and under-construction capacity.

How South Kesteven decides solar, wind and battery applications

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

All projects in South Kesteven

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG32, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.