Solar Farm at Welby Solar Farm (46 MW)

Solar Farm at Welby Solar Farm is a 46 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 February 2025, not yet built; the record was last updated on 14 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

46 MWsolar farm
approved, not builtstatus in REPD
14 February 2025record last updated
South Kestevencouncil area

Planning timeline

DateStage
21 June 2024Application submitted
10 February 2025Planning permission granted
10 February 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
46 MW
Status (REPD)
approved, not built
Record last updated
14 February 2025
Operator or applicant
Island Green Power
Planning authority
South Kesteven
Planning application reference
S24/1040
Site area
144.9 ha
Address (REPD)
Welby Solar Farm, N/O Welby, Grantham
Council area (by location)
South Kesteven
Time to decision
33 weeks
Name in REPD
Welby Solar Farm, Welby - Solar Farm
REPD reference
15193

Recorded together with Welby Solar Farm, Welby (battery storage, approved, not built).

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Side Barn, Church Lane Solar Farmsolar farm24approved, not built0.2
Glebe Farm Solar Farmsolar farm38.8refused1.5
Manor Farmbattery storage26permission expired2.7
Ash Tree Solar Farm & Battery Storagesolar farm49.9approved, not built3.3
Heath Lanesolar farm5refused5.1
High Dyke (Mill Farm)solar farm5operational6.6
Highfield Farmsolar farm17refused7.8
Gonerby Moor, Great Gonerby Solar Farmsolar farm60operational8.8
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9331, -0.549).