Energy Projects Near You

Gonerby Moor, Great Gonerby Solar Farm (60 MW)

Gonerby Moor, Great Gonerby Solar Farm is a 60 MW solar farm project in South Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 June 2026; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWsolar farm
operationalstatus in REPD
13 July 2026record last updated
South Kestevencouncil area

Planning timeline

DateStage
21 May 2021Application submitted
3 November 2021Planning permission granted
1 May 2025Construction started
26 June 2026Operational

Project details

Technology
solar farm
Capacity
60 MW
Status (REPD)
operational
Record last updated
13 July 2026
Operator or applicant
Sonnedix
Planning authority
South Kesteven
Planning application reference
S21/1018
Site area
76.2 ha
Address (REPD)
Gonerby Moor Great Gonerby
Council area (by location)
South Kesteven
Time to decision
24 weeks
Contracts for Difference
AR5
Name in REPD
Gonerby Moor, Great Gonerby - Solar Farm
REPD reference
9096

Recorded together with Gonerby Moor (battery storage, approved, not built).

Who decides

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built0.8
Pastures Farm solar park (Gonerby Lane)solar farm5permission expired1.8
Grantham Solar Farmsolar farm5operational3.6
Bypass Solar Farmsolar farm50approved, not built4.5
Sewstern Lane Wind Farmwind farm15refused5.8
Thackson's Well Wind Farmwind farm23refused6.0
Temple Hill Wind Farmwind farm15refused6.4
Manor Farmbattery storage26permission expired6.7
Highfield Farmsolar farm17refused6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9559, -0.6744).