Energy Projects Near You

Solar, wind and battery projects near Grantham (NG31)

28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG31 (South Kesteven): 3 are waiting for a planning decision, 15 approved but not yet running, 4 operational. The largest live scheme is Canners Lane Energy Park, High Dike (1,000 MW battery storage, application submitted on 23 September 2025, no decision recorded), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28projects within 10 km
3awaiting a decision
15approved, not running
4operational

Projects within 10 km of NG31

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Manor Farmbattery storagebattery storage26permission expiredupdated Mar 2023Jan 2019granted May 2019Mar 2023South Kesteven3.9
Ash Tree Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Kesteven4.0
Ash Tree Solar Farm & Battery Storagebattery storagebattery storage25approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Kesteven4.0
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farmsolar farm23approved, not builtupdated Jul 2025Oct 2023granted Jan 2024Jul 2025South Kesteven4.5
High Dyke (Mill Farm)solar farmsolar farm5operationalupdated Jan 2017Aug 2015granted Nov 2015Jan 2017South Kesteven4.6
Gonerby Moor, Great Gonerby Solar Farmsolar farmsolar farm60operationalupdated Jul 2026May 2021granted Nov 2021Jul 2026South Kesteven5.1
Pastures Farm solar park (Gonerby Lane)solar farmsolar farm5permission expiredupdated Mar 2018Feb 2015granted Jun 2015Mar 2018South Kesteven5.3
Side Barn, Church Lane Solar Farmsolar farmsolar farm24approved, not builtupdated Jan 2025Apr 2024granted Jan 2025Jan 2025South Kesteven6.4
Solar Farm at Welby Solar Farmsolar farmsolar farm46approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025South Kesteven6.6
Marston Solar Farmsolar farmsolar farm4.9operationalupdated Aug 2011Mar 2011granted May 2011Aug 2011South Kesteven6.9
Glebe Farm Solar Farmsolar farmsolar farm38.8refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025South Kesteven7.2
Heath Lanesolar farmsolar farm5refusedupdated Nov 2015Sep 2015refused Mar 2016Nov 2015South Kesteven8.1
Grantham Solar Farmsolar farmsolar farm5operationalupdated Mar 2016Apr 2015granted Jun 2015Mar 2016South Kesteven8.3
New Earth Solutions West, High Dike Solar Panels & Battery Sroragesolar farmsolar farm4.8approved, not built may be out of dateupdated Jun 2023Nov 2022granted Jan 2023Jun 2023North Kesteven8.5
Bypass Solar Farmsolar farmsolar farm50approved, not built may be out of dateupdated May 2021Aug 2020granted Mar 2021May 2021South Kesteven8.9
Canners Lane Energy Park, High Dikebattery storagebattery storage1,000application submittedupdated Oct 2025Sep 2025—Oct 2025South Kesteven9.1
Sewstern Lane Wind Farmwind farmwind farm15refusedupdated Nov 2015Apr 2015refused Oct 2015Nov 2015South Kesteven9.4
Highfield Farmsolar farmsolar farm17refusedupdated Jul 2014Mar 2014refused Jun 2014Jul 2014South Kesteven9.5
Belvoir Estate Solar farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Apr 2022refused Sep 2023Feb 2026Melton9.7
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
MV Fruehauf Limited, Houghton Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2025Mar 2025granted May 2025May 2025South Kesteven1.5
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024South Kesteven1.7
Grantham Meres Leisure Centre, Trent Roadrooftop solarrooftop solar0.2application submittedupdated Sep 2024Aug 2024—Sep 2024South Kesteven1.7
Walton Girls School, Kitty Briggs Lanerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025South Kesteven2.2
BGB Engineering Limited Solar Panels Schemerooftop solarrooftop solar0.2approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022South Kesteven2.2
Belton Garden Centre, Grantham Road Solar Arraysrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023South Kesteven3.3
Gonerby Moorbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023South Kesteven6.5
Welby Solar Farm, Welbybattery storagebattery storage—approved, not builtupdated Feb 2025Jun 2024granted Feb 2025Feb 2025South Kesteven6.6
New Earth Solutions West, High Dike Solar Panels & Battery Sroragebattery storagebattery storage—approved, not built may be out of dateupdated Jun 2023Nov 2022granted Jan 2023Jun 2023North Kesteven8.5

Distance from the average position of the NG31 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm150743248
Rooftop solar624001.5
Wind farm100010
Battery storage614001,025

MW in pipeline: pending, approved and under-construction capacity.

How South Kesteven decides solar, wind and battery applications

ApplicationsSouth KestevenUK
Decided applications (solar, wind, battery)4010,236
Refused14 (35%)19%
Solar refused9 of 3112%
Onshore wind refused4 of 445%
Battery storage refused1 of 516%
Median time from submission to decision15.0 weeks17.0 weeks
Appeals lodged / allowed3 / 5—

All projects in South Kesteven

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG31, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.