Energy Projects Near You

Solar, wind and battery projects near Newark (NG24)

27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NG24 (Newark and Sherwood): 5 are waiting for a planning decision, 11 approved but not yet running, 4 operational. The largest live scheme is Great North Road Solar Park (800 MW solar farm, application submitted on 27 June 2025, no decision recorded), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27projects within 10 km
5awaiting a decision
11approved, not running
4operational

Projects within 10 km of NG24

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hawton Wind Farmwind farmwind farm9operationalupdated Oct 2017Dec 2011granted Sep 2014Oct 2017Newark and Sherwood2.5
The Grangesolar farmsolar farm49.9operationalupdated Apr 2021Aug 2019granted Jun 2023Apr 2021Newark and Sherwood2.7
Newark Sugar Factorywind turbinewind turbine1.5application withdrawnupdated Nov 2015Jul 2015—Nov 2015Newark and Sherwood2.7
Main Street, Kelham Solar Farm & Battery Energy Storagebattery storagebattery storage50approved, not builtupdated Mar 2025Oct 2023refused Jan 2025Mar 2025Newark and Sherwood4.2
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2025Oct 2023refused Jan 2025Mar 2025Newark and Sherwood4.2
Fox Covert Wind Farmwind farmwind farm10refusedupdated Jun 2016Jul 2013refused Oct 2014Jun 2016Newark and Sherwood4.3
Staythorpe Roadbattery storagebattery storage360under constructionupdated Sep 2025Nov 2022granted May 2024Sep 2025Newark and Sherwood4.5
Staythorpe Road, Averhambattery storagebattery storage300application submitted may be out of dateupdated Mar 2023Mar 2023—Mar 2023Newark and Sherwood4.5
Grange Solar Farmsolar farmsolar farm4.6operationalupdated Aug 2011Feb 2011granted May 2011Aug 2011Newark and Sherwood4.7
Copley Farmsolar farmsolar farm30operationalupdated Mar 2016Jan 2014granted Jan 2015Mar 2016South Kesteven6.7
Copley Farmsolar farmsolar farm10.1abandonedupdated Jan 2016Aug 2014granted Dec 2014Jan 2016South Kesteven6.7
Great North Road Solar Parksolar farmsolar farm800application submittedupdated Oct 2025Jun 2025—Oct 2025Newark and Sherwood7.8
Foxholes Farm, Bathley Lane Solar Farmsolar farmsolar farm49.9refusedupdated Jul 2026Nov 2022refused May 2026Jul 2026Newark and Sherwood8.1
Hockerton Road, Caunton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Apr 2025Jun 2022granted Mar 2025Apr 2025Newark and Sherwood8.5
Knapthorpe Grange, Caunton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Apr 2025Jun 2022granted Mar 2025Apr 2025Newark and Sherwood8.6
Lodge Farm (Lincolnshire)wind farmwind farm3.9application withdrawnupdated Jun 2011Mar 2011—Jun 2011North Kesteven8.9
Tuxford Road Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Jul 2021granted Dec 2021Apr 2022Newark and Sherwood9.3
Fulbeck Airfield Wind Farmwind farmwind farm25refusedupdated Apr 2017Aug 2015refused Mar 2017Apr 2017South Kesteven9.3
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sleaford Road, Newark On Trentbattery storagebattery storage0.2application submittedApr 2026——Newark and Sherwood0.9
Blueprint Gaming, Northern Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Newark and Sherwood1.3
Flowserve Pump Division, Balderton -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Newark and Sherwood1.3
London Road - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Mar 2026—May 2026Newark and Sherwood1.9
The Scrapyard, Bowbridge Lanebattery storagebattery storage—approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024Newark and Sherwood2.5
Barnby Manorsolar farmsolar farm0.2permission expiredupdated Jun 2019Mar 2019granted Oct 2019Jun 2019Newark and Sherwood5.7
Flash Farm, Micklebarrow Hillsolar farmsolar farm0.1approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Newark and Sherwood6.2
Great North Road Solar Parkbattery storagebattery storage—application submittedupdated Oct 2025Jun 2025—Oct 2025Newark and Sherwood7.8
Tuxford Road Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Mar 2021Jul 2021granted Dec 2021Mar 2021Newark and Sherwood9.3

Distance from the average position of the NG24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1215311,000
Rooftop solar202000.6
Wind farm400120
Wind turbine100000
Battery storage84400710

MW in pipeline: pending, approved and under-construction capacity.

How Newark and Sherwood decides solar, wind and battery applications

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

All projects in Newark and Sherwood

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NG24, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.