Energy Projects Near You

Knapthorpe Grange, Caunton Solar Farm (49.9 MW)

Knapthorpe Grange, Caunton Solar Farm is a 49.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 31 March 2025, not yet built; the record was last updated on 23 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
23 April 2025record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
1 June 2022Application submitted
17 November 2023Refused by the planning authority
16 August 2024Appeal lodged
31 March 2025Planning permission granted
31 March 2025Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
23 April 2025
Operator or applicant
Knapthorpe Solar Limited
Planning authority
Newark and Sherwood
Planning application reference
22/00975/FULM
Appeal reference
24/00035/DEC
Site area
74.4 ha
Address (REPD)
Knapthorpe Lodge, Hockerton Road, Caunton, Newark On Trent
Council area (by location)
Newark and Sherwood
Time to decision
148 weeks
Name in REPD
Knapthorpe Grange, Caunton - Solar Farm
REPD reference
9894

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built0.7
Foxholes Farm, Bathley Lane Solar Farmsolar farm49.9refused4.3
Tuxford Road Solar Farmsolar farm49.9approved, not built4.4
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farm49.9approved, not built4.4
Winkburn Estate Solar Farmsolar farm49.9under construction4.5
Staythorpe Road, Averhambattery storage300application submitted4.9
Staythorpe Roadbattery storage360under construction4.9
Great North Road Solar Parksolar farm800application submitted5.8
Stud Solar Farmsolar farm25permission expired7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1205, -0.8949).