Foxholes Farm, Bathley Lane Solar Farm (49.9 MW)

Foxholes Farm, Bathley Lane Solar Farm is a 49.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 May 2026; the record was last updated on 10 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
refusedstatus in REPD
10 July 2026record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
28 November 2022Application submitted
8 May 2026Refused by the planning authority

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
10 July 2026
Operator or applicant
Elgin Energy
Planning authority
Newark and Sherwood
Planning application reference
22/01983/FULM
Site area
75.4 ha
Address (REPD)
Foxholes Farm, Bathley Lane, North Muskham
Council area (by location)
Newark and Sherwood
Time to decision
180 weeks
Name in REPD
Foxholes Farm, Bathley Lane - Solar Farm
REPD reference
12881

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tuxford Road Solar Farmsolar farm49.9approved, not built1.3
Great North Road Solar Parksolar farm800application submitted1.6
Stud Solar Farmsolar farm25permission expired3.9
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built4.3
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built4.9
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farm49.9approved, not built5.0
Staythorpe Roadbattery storage360under construction6.5
Staythorpe Road, Averhambattery storage300application submitted6.5
Winkburn Estate Solar Farmsolar farm49.9under construction8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1379, -0.8367).