Tuxford Road Solar Farm (49.9 MW)

Tuxford Road Solar Farm is a 49.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 December 2021, not yet built; the record was last updated on 6 April 2022. REPD records the planning permission as expiring on 16 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
6 April 2022record last updated
Newark and Sherwoodcouncil area

REPD records the planning permission as expiring on 16 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
16 July 2021Application submitted
16 December 2021Planning permission granted
16 December 2024Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
6 April 2022
Operator or applicant
Enso Energy Limited
Planning authority
Newark and Sherwood
Planning application reference
21/01577/FULM
Site area
120.7 ha
Address (REPD)
Land North And South Tuxford Road Skegby
Council area (by location)
Newark and Sherwood
Time to decision
22 weeks
Contracts for Difference
AR4
REPD reference
8503

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Foxholes Farm, Bathley Lane Solar Farmsolar farm49.9refused1.3
Great North Road Solar Parksolar farm800application submitted2.5
Stud Solar Farmsolar farm25permission expired3.0
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built4.4
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built5.0
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farm49.9approved, not built6.0
Egmanton Solar Farmsolar farm14.2operational7.4
Staythorpe Roadbattery storage360under construction7.4
Staythorpe Road, Averhambattery storage300application submitted7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1476, -0.8477).