Energy Projects Near You

Egmanton Solar Farm (14.2 MW)

Egmanton Solar Farm is a 14.2 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.2 MWsolar farm
operationalstatus in REPD
4 October 2016record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
5 June 2014Application submitted
23 July 2014Planning permission granted
1 December 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
14.2 MW
Status (REPD)
operational
Record last updated
4 October 2016
Operator or applicant
United Photovoltaics
Planning authority
Newark and Sherwood
Planning application reference
14/00975/FULM
Site area
23.6 ha
Address (REPD)
Land Between Weston Road, And The A1, Egmanton,
Council area (by location)
Newark and Sherwood
Time to decision
7 weeks
REPD reference
2321

Earlier applications for this site

ApplicationMWSubmittedOutcome
Egmanton Solar Farm 13/01422/FULM142 December 2013refused 15 May 2014

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Westwood Farm Solar Parksolar farm5.1operational3.4
Polly Taylors Road, High Marnhambattery storage400application submitted3.9
America Farm, Woodcoates Road Solar Farmsolar farm49.9application submitted5.0
Stud Solar Farmsolar farm25permission expired5.3
High Marnham Solar Photovoltaic Farmsolar farm42.7approved, not built5.5
One Earth Solar Farmsolar farm740approved, not built5.9
Long Ridding Lane, East Drayton Solar Farmsolar farm49.9application submitted7.1
Tuxford Road Solar Farmsolar farm49.9approved, not built7.4
Drayton Road, Upton Solar Farmsolar farm49.9application submitted8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2113, -0.8798).