Energy Projects Near You

High Marnham Solar Photovoltaic Farm (42.7 MW)

High Marnham Solar Photovoltaic Farm is a 42.7 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 January 2023, not yet built; the record was last updated on 6 June 2022. REPD also records that the planning permission expired on 5 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42.7 MWsolar farm
approved, not builtmay be out of datestatus in REPD
6 June 2022record last updated
Bassetlawcouncil area

REPD also records that the planning permission expired on 5 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
17 May 2022Application submitted
5 January 2023Planning permission granted
5 January 2026Permission expired

Project details

Technology
solar farm
Capacity
42.7 MW
Status (REPD)
approved, not built
Record last updated
6 June 2022
Operator or applicant
J G Pears Property Limited
Planning authority
Bassetlaw
Planning application reference
22/00707/FUL
Site area
58.1 ha
Address (REPD)
Adj Former High Marnham Power Station High Marnham
Council area (by location)
Bassetlaw
Time to decision
33 weeks
Name in REPD
High Marnham - Solar Photovoltaic Farm
REPD reference
11392

Who decides

ApplicationsBassetlawUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused0 of 2512%
Onshore wind refused5 of 745%
Battery storage refused0 of 816%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
One Earth Solar Farmsolar farm740approved, not built0.7
Polly Taylors Road, High Marnhambattery storage400application submitted1.6
America Farm, Woodcoates Road Solar Farmsolar farm49.9application submitted1.7
Long Ridding Lane, East Drayton Solar Farmsolar farm49.9application submitted5.3
Egmanton Solar Farmsolar farm14.2operational5.5
Stud Solar Farmsolar farm25permission expired6.4
Torksey Ferry Road, Ramptonbattery storage500approved, not built7.9
Drayton Road, Upton Solar Farmsolar farm49.9application submitted8.0
Cottam Power Stationbattery storage49approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2272, -0.8018).