One Earth Solar Farm (740 MW)

One Earth Solar Farm is a 740 MW solar farm project in Bassetlaw, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 July 2026, not yet built; the record was last updated on 13 July 2026. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010159).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

740 MWsolar farm
approved, not builtstatus in REPD
13 July 2026record last updated
Bassetlawcouncil area

Planning timeline

DateStage
27 February 2025Application submitted
8 July 2026Development consent granted (Secretary of State)
8 July 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
740 MW
Status (REPD)
approved, not built
Record last updated
13 July 2026
Operator or applicant
Orsted UK Limited / PS Renewables
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010159
Site area
1,409.0 ha
Address (REPD)
High Marnham, The border of Nottinghamshire, Newark
Council area (by location)
Bassetlaw
Time to decision
71 weeks
REPD reference
14806

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010159)

Yes, One Earth near High Marnham in Bassetlaw is approved, and the decision is recent. The 740 MW application from Orsted UK Limited and PS Renewables was submitted on 27 February 2025, and after examination by the Planning Inspectorate (EN010159) the Energy Secretary granted the development consent order (DCO) on 8 July 2026. The post was held at the time by Ed Miliband. That came to 71 weeks, against the Inspectorate's median of 73 across 46 decided applications.

What the decision means

According to the REPD record (July 2026 extract), construction has not started. If work on the 1,409 hectares does not begin by 8 July 2031, the consent will expire. The scheme's battery storage is recorded separately: approved, not built. There is no site map in the data, only the record's point on the mini-map.

The cluster around High Marnham

At 0.7 km, the 42.7 MW solar farm High Marnham is approved. Among battery schemes, Polly Taylors Road at 400 MW is awaiting a decision, while Torksey Ferry Road in Rampton (500 MW) and Cottam Power Station (49 MW) are approved. The nearest residential postcode district, NG23, lies 11.8 km away.

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010159). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
High Marnham Solar Photovoltaic Farmsolar farm42.7approved, not built0.7
Polly Taylors Road, High Marnhambattery storage400application submitted2.0
America Farm, Woodcoates Road Solar Farmsolar farm49.9application submitted2.4
Egmanton Solar Farmsolar farm14.2operational5.9
Long Ridding Lane, East Drayton Solar Farmsolar farm49.9application submitted6.0
Stud Solar Farmsolar farm25permission expired6.1
Torksey Ferry Road, Ramptonbattery storage500approved, not built8.4
Cottam Power Stationbattery storage49approved, not built8.6
Drayton Road, Upton Solar Farmsolar farm49.9application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2226, -0.7935).