Stud Solar Farm (25 MW)

Stud Solar Farm is a 25 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 15 June 2018; the record was last updated on 19 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
permission expiredstatus in REPD
19 July 2018record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
19 February 2015Application submitted
15 June 2015Planning permission granted
15 June 2018Permission expired

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
permission expired
Record last updated
19 July 2018
Operator or applicant
Martifer Solar (Voltalia)
Planning authority
Newark and Sherwood
Planning application reference
15/00324/FULM
Site area
38.6 ha
Address (REPD)
Stud Farm, Ossington Road, Carlton On Trent
Council area (by location)
Newark and Sherwood
Time to decision
17 weeks
REPD reference
4809

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tuxford Road Solar Farmsolar farm49.9approved, not built3.0
Foxholes Farm, Bathley Lane Solar Farmsolar farm49.9refused3.9
Great North Road Solar Parksolar farm800application submitted4.0
Egmanton Solar Farmsolar farm14.2operational5.3
Polly Taylors Road, High Marnhambattery storage400application submitted5.5
One Earth Solar Farmsolar farm740approved, not built6.1
High Marnham Solar Photovoltaic Farmsolar farm42.7approved, not built6.4
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built7.1
America Farm, Woodcoates Road Solar Farmsolar farm49.9application submitted7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1728, -0.833).