Energy Projects Near You

Renewable energy projects in Newark and Sherwood

48 solar, wind or battery projects of 150 kW or more are located in Newark and Sherwood (REPD, July 2026 extract): 6 pending, 21 approved but not running, 13 operational and 4 refused. The council refused 16 of 41 decided applications (39%; UK 19%), with a median 23 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48projects in the council area
6awaiting a decision
21approved, not running
39%of decisions refused

How Newark and Sherwood decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Projects in Newark and Sherwood

Projects of 1 MW and more (31)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Great North Road Solar Parksolar farmsolar farm800application submittedupdated Oct 2025Jun 2025—Oct 2025
Staythorpe Roadbattery storagebattery storage360under constructionupdated Sep 2025Nov 2022granted May 2024Sep 2025
Staythorpe Road, Averhambattery storagebattery storage300application submitted may be out of dateupdated Mar 2023Mar 2023—Mar 2023
Main Street, Kelham Solar Farm & Battery Energy Storagebattery storagebattery storage50approved, not builtupdated Mar 2025Oct 2023refused Jan 2025Mar 2025
Inkersall Grange Farmsolar farmsolar farm49.9operationalupdated Jul 2026Jul 2019granted Sep 2019Jul 2026
The Grangesolar farmsolar farm49.9operationalupdated Apr 2021Aug 2019granted Jun 2023Apr 2021
Winkburn Estate Solar Farmsolar farmsolar farm49.9under constructionupdated Jul 2026Dec 2020granted May 2021Jul 2026
Cotmoor Lanesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2022Jul 2020granted Feb 2022Feb 2022
Tuxford Road Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Jul 2021granted Dec 2021Apr 2022
Knapthorpe Grange, Caunton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Apr 2025Jun 2022granted Mar 2025Apr 2025
Hockerton Road, Caunton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Apr 2025Jun 2022granted Mar 2025Apr 2025
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2025Oct 2023refused Jan 2025Mar 2025
Foxholes Farm, Bathley Lane Solar Farmsolar farmsolar farm49.9refusedupdated Jul 2026Nov 2022refused May 2026Jul 2026
Stud Solar Farmsolar farmsolar farm25permission expiredupdated Jul 2018Feb 2015granted Jun 2015Jul 2018
Welbeck Solar / Hazel Gapsolar farmsolar farm16operationalupdated Aug 2015Aug 2014granted Jan 2015Aug 2015
Lindhurst Wind Farmwind farmwind farm15operationalupdated Dec 2010Jun 2006granted Sep 2007Dec 2010
Egmanton Solar Farmsolar farmsolar farm14.2operationalupdated Oct 2016Jun 2014granted Jul 2014Oct 2016
Eakring Solar Farmsolar farmsolar farm11.9operationalupdated May 2015May 2014granted Oct 2014May 2015
Stonish Hill (Bilsthorpe)wind farmwind farm10.3operationalupdated Aug 2017Jun 2007granted Mar 2009Aug 2017
Fox Covert Wind Farmwind farmwind farm10refusedupdated Jun 2016Jul 2013refused Oct 2014Jun 2016
Hawton Wind Farmwind farmwind farm9operationalupdated Oct 2017Dec 2011granted Sep 2014Oct 2017
Rufford Solar Farmsolar farmsolar farm5refusedupdated Dec 2015Sep 2015refused Dec 2015Dec 2015
Bilsthorpe (Land off Forest Lane)solar farmsolar farm5operationalupdated Jul 2017Aug 2015granted Jan 2016Jul 2017
Bilsthorpe Quarry Solar Parksolar farmsolar farm4.8operationalupdated Feb 2015Dec 2012granted Aug 2013Feb 2015
Grange Solar Farmsolar farmsolar farm4.6operationalupdated Aug 2011Feb 2011granted May 2011Aug 2011
Land South Off Ollerton Roadsolar farmsolar farm4.2operationalupdated Mar 2017May 2015granted Jun 2016Mar 2017
Featherstone House Farmsolar farmsolar farm3.2approved, not built may be out of dateupdated Oct 2018Aug 2013granted Apr 2016Oct 2018
Rufford Lanesolar farmsolar farm2.6operationalupdated Jun 2016Jan 2015granted May 2015Jun 2016
Belle Eau Parksolar farmsolar farm1.9permission expiredupdated Aug 2018Oct 2014granted Jan 2015Aug 2018
Newark Sugar Factorywind turbinewind turbine1.5application withdrawnupdated Nov 2015Jul 2015—Nov 2015
South East of Wadnal Lanewind turbinewind turbine1.3refused on appealupdated Jul 2015May 2014refused Jun 2015Jul 2015
Smaller schemes under 1 MW, mostly rooftop solar (17)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Ossington Road, Carlton On Trent- Solar Panelsrooftop solarrooftop solar0.9approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Clay Farm, South Scarle Lanerooftop solarrooftop solar0.6approved, not builtupdated Feb 2023Jan 2023granted Feb 2023Feb 2023
Orston Shooting Ground, Bottesford Lanebattery storagebattery storage0.4approved, not builtupdated Mar 2026Mar 2025granted Feb 2026Mar 2026
Flowserve Pump Division, Balderton -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026
Blueprint Gaming, Northern Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025
Trentholme Farm, North Cliftonwind turbinewind turbine0.2application submittedupdated Mar 2026Jan 2026—Mar 2026
Barnby Manorsolar farmsolar farm0.2permission expiredupdated Jun 2019Mar 2019granted Oct 2019Jun 2019
Newark Road, Wellow - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
London Road - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Mar 2026—May 2026
Sleaford Road, Newark On Trentbattery storagebattery storage0.2application submittedApr 2026——
Orston Shooting Ground, Bottesford Lanesolar farmsolar farm0.2approved, not builtupdated Mar 2026Mar 2025granted Feb 2026Mar 2026
Flash Farm, Micklebarrow Hillsolar farmsolar farm0.1approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023
Cotmoor Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Sep 2020Jul 2020granted Feb 2022Sep 2020
Tuxford Road Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Mar 2021Jul 2021granted Dec 2021Mar 2021
Winkburn Lane, Winkburnbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023
Great North Road Solar Parkbattery storagebattery storage—application submittedupdated Oct 2025Jun 2025—Oct 2025
The Scrapyard, Bowbridge Lanebattery storagebattery storage—approved, not builtupdated Sep 2024Dec 2023granted Aug 2024Sep 2024

Postcode districts in Newark and Sherwood

DistrictProjects within 10 kmPendingApprovedOperational
NG213311213
NG222411010
NG23315173
NG24275114
NG25191116

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Newark and Sherwood by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.