Energy Projects Near You

Stonish Hill (Bilsthorpe) (10.3 MW wind farm)

Stonish Hill (Bilsthorpe) is a 10.3 MW wind farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 1 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.3 MWwind farm
operationalstatus in REPD
1 August 2017record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
8 June 2007Application submitted
6 March 2008Refused by the planning authority
16 March 2009Planning permission granted
16 March 2009Appeal allowed
25 June 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
10.3 MW
Status (REPD)
operational
Record last updated
1 August 2017
Operator or applicant
REG Power Management (John Laing/Peel Energy)
Planning authority
Newark and Sherwood
Planning application reference
07/00856/FULEIA
Appeal reference
APP/B3030/A/08/2072487/NWF
Turbines
5
Address (REPD)
Former Bilsthorpe Colliery Eakring Road Bilsthorpe
Council area (by location)
Newark and Sherwood
Time to decision
92 weeks
REPD reference
3739

Earlier applications for this site

ApplicationMWSubmittedOutcome
Stonish Hill141 December 2005refused 1 November 2006

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eakring Solar Farmsolar farm11.9operational0.4
Bilsthorpe (Land off Forest Lane)solar farm5operational3.2
Inkersall Grange Farmsolar farm49.9operational4.3
Winkburn Estate Solar Farmsolar farm49.9under construction5.0
Rufford Solar Farmsolar farm5refused6.7
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built8.7
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built8.7
Lindhurst Wind Farmwind farm15operational9.9
Westwood Farm Solar Parksolar farm5.1operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1511, -1.0146).