Energy Projects Near You

Rufford Solar Farm (5 MW)

Rufford Solar Farm is a 5 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 December 2015; the record was last updated on 16 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
16 December 2015record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
16 September 2015Application submitted
10 December 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
16 December 2015
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Newark and Sherwood
Planning application reference
15/01008/FULM
Site area
18.8 ha
Address (REPD)
Rufford Colliery Lane, Rainworth, Mansfield
Council area (by location)
Newark and Sherwood
Time to decision
12 weeks
REPD reference
4849

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Inkersall Grange Farmsolar farm49.9operational2.7
Lindhurst Wind Farmwind farm15operational3.2
Bilsthorpe (Land off Forest Lane)solar farm5operational4.3
Two Oaks Quarrysolar farm5permission expired6.6
Stonish Hill (Bilsthorpe)wind farm10.3operational6.7
Eakring Solar Farmsolar farm11.9operational6.8
Hamilton Road Solar Farmsolar farm7refused8.0
Land At Debdale Lanesolar farm5operational8.1
Littlewood Lane Solarsolar farm5operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1283, -1.1068).