Land At Debdale Lane (5 MW solar farm)

Land At Debdale Lane is a 5 MW solar farm project in Mansfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2016; the record was last updated on 1 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 August 2016record last updated
Mansfieldcouncil area

Planning timeline

DateStage
22 July 2015Application submitted
21 October 2015Planning permission granted
15 January 2016Construction started
25 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 August 2016
Operator or applicant
Equitix Fund IV
Planning authority
Mansfield
Planning application reference
2015/0449/NT
Site area
17.8 ha
Address (REPD)
Land At Debdale Lane, Burlington Drive, Mansfield, Nottinghamshire
Council area (by location)
Mansfield
Time to decision
13 weeks
REPD reference
5401

Who decides

ApplicationsMansfieldUK
Decided applications (solar, wind, battery)1510,236
Refused3 (20%)19%
Solar refused3 of 1412%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ashland Solar Farmsolar farm5permission expired2.3
Littlewood Lane Solarsolar farm5operational2.5
Hamilton Road Solar Farmsolar farm7refused4.1
Land West Of Sookholme Roadsolar farm10refused4.3
Roseland Community Wind Farmwind farm12refused5.1
Two Oaks Quarrysolar farm5permission expired6.0
Lindhurst Wind Farmwind farm15operational6.4
Brecks Solar Farmsolar farm45.4approved, not built6.5
Losk Lanewind farm5refused7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1602, -1.2161).