Roseland Community Wind Farm (12 MW)

Roseland Community Wind Farm is a 12 MW wind farm project in Bolsover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 July 2013; the record was last updated on 17 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
17 March 2015record last updated
Bolsovercouncil area

Planning timeline

DateStage
25 April 2012Application submitted
19 July 2013Refused by the planning authority
30 January 2014Appeal lodged
1 June 2014Secretary of State intervened
16 March 2015Secretary of State refused

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
17 March 2015
Operator or applicant
Roseland Community Energy Trust
Planning authority
Bolsover
Planning application reference
12/00159/FULEA
Appeal reference
APP/R1010/A/14/2212093
Turbines
6
Address (REPD)
Roseland, Derby, Derbyshire, S44.
Council area (by location)
Bolsover
Time to decision
64 weeks
REPD reference
4533

Who decides

ApplicationsBolsoverUK
Decided applications (solar, wind, battery)2010,236
Refused4 (20%)19%
Solar refused2 of 1212%
Onshore wind refused2 of 245%
Battery storage refused0 of 616%
Median time from submission to decision12.5 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Losk Lanewind farm5refused2.2
Stockley Hill Solar Farmsolar farm5refused2.8
Littlewood Lane Solarsolar farm5operational4.1
Land at Bolsover Moor Quarrysolar farm5operational4.6
Land West Of Sookholme Roadsolar farm10refused4.9
Land At Debdale Lanesolar farm5operational5.1
Frithwood Farm, Frithwood Lane Solar Farmsolar farm25approved, not built5.9
Ashland Solar Farmsolar farm5permission expired6.2
Brecks Solar Farmsolar farm45.4approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1981, -1.2582).