Energy Projects Near You

Stockley Hill Solar Farm (5 MW)

Stockley Hill Solar Farm is a 5 MW solar farm project in Bolsover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 11 February 2016; the record was last updated on 4 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
4 March 2015record last updated
Bolsovercouncil area

Planning timeline

DateStage
2 October 2015Application submitted
11 February 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
4 March 2015
Operator or applicant
Stockley Hill Solar Farm
Planning authority
Bolsover
Planning application reference
15/00366/FUL
Site area
7.3 ha
Address (REPD)
Land to south and e/o Rylah Farm, Rylah, Palterton, Chesterfield
Council area (by location)
Bolsover
Time to decision
19 weeks
REPD reference
5839

Who decides

ApplicationsBolsoverUK
Decided applications (solar, wind, battery)2010,236
Refused4 (20%)19%
Solar refused2 of 1212%
Onshore wind refused2 of 245%
Battery storage refused0 of 616%
Median time from submission to decision12.5 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Losk Lanewind farm5refused0.7
Roseland Community Wind Farmwind farm12refused2.8
Cherry Tree Farmsolar farm5operational4.6
Land at Bolsover Moor Quarrysolar farm5operational5.0
Calow Green Farmbattery storage20operational5.3
Land To The East Of Back Lanesolar farm5operational5.6
Lings Farm, Birkin Lanesolar farm9application submitted5.7
Arkwright Solar Farmsolar farm8operational5.8
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2044, -1.2995).