Energy Projects Near You

Arkwright Solar Farm (8 MW)

Arkwright Solar Farm is an 8 MW solar farm project in Chesterfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 December 2015; the record was last updated on 15 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
15 December 2015record last updated
Chesterfieldcouncil area

Planning timeline

DateStage
15 September 2014Application submitted
24 February 2015Planning permission granted
1 June 2015Construction started
18 December 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
15 December 2015
Operator or applicant
Conergy
Planning authority
Chesterfield
Planning application reference
CHE/14/00644/FUL
Site area
19.5 ha
Address (REPD)
Land To West Of Duckmanton and North Of Tom Lane Chesterfield Derbyshire
Council area (by location)
Chesterfield
Time to decision
23 weeks
REPD reference
2107

Who decides

ApplicationsChesterfieldUK
Decided applications (solar, wind, battery)1510,236
Refused0 (0%)19%
Solar refused0 of 1212%
Battery storage refused0 of 316%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Chesterfield, Hampshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cherry Tree Farmsolar farm5operational1.2
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagesolar farm31operational1.3
Lodge Farm, Calowbattery storage25approved, not built2.6
Land To The East Of Back Lanesolar farm5operational3.0
Calow Green Farmbattery storage20operational3.5
The Brecksolar farm5operational3.8
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built4.5
Land South East of Low Common Farmsolar farm8.3refused5.2
Stockley Hill Solar Farmsolar farm5refused5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2479, -1.3464).