Hasland Photovoltaic Solar Park (49.9 MW)
Hasland Photovoltaic Solar Park is a 49.9 MW solar farm project in North East Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 December 2021, not yet built; the record was last updated on 20 May 2024. REPD records the planning permission as expiring on 8 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.
REPD records the planning permission as expiring on 8 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.
Planning timeline
| Date | Stage |
|---|---|
| 21 December 2020 | Application submitted |
| 8 December 2021 | Planning permission granted |
| 8 December 2024 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 49.9 MW
- Status (REPD)
- approved, not built
- Record last updated
- 20 May 2024
- Operator or applicant
- Kronos Solar
- Planning authority
- North East Derbyshire
- Planning application reference
- 20/01283/FL
- Site area
- 68.8 ha
- Address (REPD)
- Manor House Farm, Mansfield Road, Hasland, Chesterfield
- Council area (by location)
- North East Derbyshire
- Time to decision
- 50 weeks
- Contracts for Difference
- AR4
- REPD reference
- 7887
Who decides
| Applications | North East Derbyshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 29 | 10,236 |
| Refused | 5 (17%) | 19% |
| Solar refused | 1 of 19 | 12% |
| Battery storage refused | 4 of 10 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Calow Green Farm | battery storage | 20 | operational | 1.1 |
| Land To The East Of Back Lane | solar farm | 5 | operational | 1.5 |
| Lings Farm, Birkin Lane | solar farm | 9 | application submitted | 1.9 |
| Lodge Farm, Calow | battery storage | 25 | approved, not built | 2.1 |
| Langer Lane Solar Farm | solar farm | 7.5 | approved, not built | 3.6 |
| Cherry Tree Farm | solar farm | 5 | operational | 3.9 |
| Arkwright Solar Farm | solar farm | 8 | operational | 4.5 |
| Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storage | solar farm | 31 | operational | 5.8 |
| Stockley Hill Solar Farm | solar farm | 5 | refused | 6.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2164, -1.389).