Langer Lane Solar Farm (7.5 MW)

Langer Lane Solar Farm is a 7.5 MW solar farm project in North East Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 April 2025, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
North East Derbyshirecouncil area

Planning timeline

DateStage
12 July 2024Application submitted
17 April 2025Planning permission granted
17 April 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Ethical Power Development Limited
Planning authority
North East Derbyshire
Planning application reference
24/00506/MFL
Site area
9.8 ha
Address (REPD)
E/O Langer Lane, Wingerworth, Chesterfield
Council area (by location)
North East Derbyshire
Time to decision
40 weeks
Contracts for Difference
AR7a
REPD reference
16745

Who decides

ApplicationsNorth East DerbyshireUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Solar refused1 of 1912%
Battery storage refused4 of 1016%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built3.6
Lings Farm, Birkin Lanesolar farm9application submitted3.8
Calow Green Farmbattery storage20operational4.7
Land To The East Of Back Lanesolar farm5operational4.9
Lodge Farm, Calowbattery storage25approved, not built5.1
Cherry Tree Farmsolar farm5operational7.3
Land North of the Wood at Averill Farmsolar farm5operational7.4
Padleywood Farmsolar farm5operational7.5
Averhill Farmsolar farm5operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2076, -1.4407).