Energy Projects Near You

Averhill Farm (5 MW solar farm)

Averhill Farm is a 5 MW solar farm project in North East Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 December 2015; the record was last updated on 22 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 February 2016record last updated
North East Derbyshirecouncil area

Planning timeline

DateStage
28 April 2015Application submitted
29 September 2015Planning permission granted
4 November 2015Construction started
16 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 February 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
North East Derbyshire
Planning application reference
15/00307/FL
Site area
11.8 ha
Address (REPD)
Averill Farm, Evershill Lane, Morton, Alfreton
Council area (by location)
North East Derbyshire
Time to decision
22 weeks
REPD reference
5287

Who decides

ApplicationsNorth East DerbyshireUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Solar refused1 of 1912%
Battery storage refused4 of 1016%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Padleywood Farmsolar farm5operational<0.1
Land North of the Wood at Averill Farmsolar farm5operational0.6
Eden Meadows, Stretton Road, Morton Solar PV Panels & Battery Energy Storage Systemsolar farm49.9refused1.1
Hurst Farm, Mansfield Roadbattery storage99.9approved, not built3.9
Alfreton Solar Farmsolar farm25application withdrawn4.0
Newton Wood Farmbattery storage49.9approved, not built4.5
Meadow Lane Solar Farmsolar farm19.6under construction4.6
Twin Yards Solar Farmsolar farm5operational5.5
Hall Farm Solar Farmsolar farm50refused5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1481, -1.387).