Hall Farm Solar Farm (50 MW)

Hall Farm Solar Farm is a 50 MW solar farm project in Amber Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 December 2022; the record was last updated on 14 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
refusedstatus in REPD
14 December 2021record last updated
Amber Valleycouncil area

Planning timeline

DateStage
7 January 2021Application submitted
5 December 2022Refused by the planning authority

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
refused
Record last updated
14 December 2021
Operator or applicant
Kronos Solar
Planning authority
Amber Valley
Planning application reference
AVA/2020/1224
Site area
101.4 ha
Address (REPD)
Hall Farm Church Street Alfreton
Council area (by location)
Amber Valley
Time to decision
100 weeks
REPD reference
9509

Who decides

ApplicationsAmber ValleyUK
Decided applications (solar, wind, battery)2010,236
Refused6 (30%)19%
Solar refused6 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Meadow Lane Solar Farmsolar farm19.6under construction1.6
Alfreton Solar Farmsolar farm25application withdrawn1.7
Eden Meadows, Stretton Road, Morton Solar PV Panels & Battery Energy Storage Systemsolar farm49.9refused4.6
Twin Yards Solar Farmsolar farm5operational5.3
Derby Roadsolar farm38application submitted5.4
Land North of the Wood at Averill Farmsolar farm5operational5.4
Padleywood Farmsolar farm5operational5.6
Averhill Farmsolar farm5operational5.6
Former Langton Colliery Sitesolar farm5.7permission expired6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0982, -1.3931).