51 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DE55 (Amber Valley): 6 are waiting for a planning decision, 24 approved but not yet running, 5 operational. The largest live scheme is Hurst Farm, Mansfield Road (99.9 MW battery storage, approved on 19 December 2025, not yet built), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51projects within 10 km
6awaiting a decision
24approved, not running
5operational

Projects within 10 km of DE55

Projects of 1 MW and more (30)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Meadow Lane Solar Farmsolar farmsolar farm19.6under constructionupdated Dec 2021Apr 2021granted Oct 2021Dec 2021Amber Valley0.6
Hall Farm Solar Farmsolar farmsolar farm50refusedupdated Dec 2021Jan 2021refused Dec 2022Dec 2021Amber Valley1.4
Guilford Europe, Cotes Park Lanerooftop solarrooftop solar2.4approved, not builtupdated Apr 2023Jan 2023granted Apr 2023Apr 2023Amber Valley1.7
Fairbrook House, Clover Nook Roadrooftop solarrooftop solar1.1approved, not builtupdated May 2024Jan 2024granted May 2024May 2024Bolsover2.2
Alfreton Solar Farmsolar farmsolar farm25application withdrawnupdated Jan 2021Dec 2020—Jan 2021North East Derbyshire2.2
Alfreton Solar Farmbattery storagebattery storage25application withdrawnupdated Apr 2022Dec 2020—Apr 2022North East Derbyshire2.2
Twin Yards Solar Farmsolar farmsolar farm5operationalupdated Oct 2017Jul 2015granted Sep 2015Oct 2017Bolsover3.9
Eden Meadows, Stretton Road, Morton Solar PV Panels & Battery Energy Storage Systemsolar farmsolar farm49.9refusedupdated Jun 2025Dec 2023refused May 2025Jun 2025North East Derbyshire4.3
Crow Trees Farmsolar farmsolar farm4.7operationalupdated Sep 2018Apr 2014granted Jun 2014Sep 2018Ashfield5.0
Former Langton Colliery Sitesolar farmsolar farm5.7permission expiredupdated Sep 2019Mar 2016granted Jun 2016Sep 2019Ashfield5.0
Padleywood Farmsolar farmsolar farm5operationalupdated Aug 2016Mar 2015granted Aug 2015Aug 2016North East Derbyshire5.1
Averhill Farmsolar farmsolar farm5operationalupdated Feb 2016Apr 2015granted Sep 2015Feb 2016North East Derbyshire5.1
Land North of the Wood at Averill Farmsolar farmsolar farm5operationalupdated Jun 2016Jul 2015granted Oct 2015Jun 2016North East Derbyshire5.1
Swanwick Collierysolar farmsolar farm1.3application submitted may be out of dateupdated Sep 2016Jul 2015—Sep 2016Amber Valley5.1
Fulwood Grange Farmsolar farmsolar farm5abandonedupdated May 2020Jul 2015granted Nov 2015May 2020Ashfield5.2
Newton Wood Farmbattery storagebattery storage49.9approved, not built may be out of dateupdated Mar 2025May 2020granted Oct 2020Mar 2025Bolsover5.3
Whiteborough Farmsolar farmsolar farm2.2abandonedupdated Jun 2019Aug 2015granted Feb 2016Jun 2019Ashfield5.6
Hurst Farm, Mansfield Roadbattery storagebattery storage99.9approved, not builtupdated Jan 2026Jul 2025granted Dec 2025Jan 2026Bolsover5.7
Derby Roadbattery storagebattery storage40application submittedupdated Apr 2025Mar 2025—Apr 2025Amber Valley6.3
Derby Roadsolar farmsolar farm38application submittedupdated Apr 2025Mar 2025—Apr 2025Amber Valley6.3
Smithybrook Viewbattery storagebattery storage1.2permission expiredupdated Mar 2023Feb 2018granted May 2018Mar 2023North East Derbyshire7.5
Two Dales Farmsolar farmsolar farm4refusedupdated May 2016Jul 2015refused Mar 2016May 2016Ashfield7.8
Iron Works Farmsolar farmsolar farm5refusedupdated Jul 2013Nov 2012refused Jul 2013Jul 2013Amber Valley8.0
Hl Plastics Extrusions, Flamstead House Hall Roadrooftop solarrooftop solar4.1approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Amber Valley8.5
Romo, Oddicroft Lanerooftop solarrooftop solar1approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Ashfield8.5
Home Farmsolar farmsolar farm1.9refusedupdated Nov 2015Jul 2015refused Oct 2015Nov 2015Amber Valley8.6
Knob Farmsolar farmsolar farm5refusedupdated Jul 2013Nov 2012refused Jul 2013Jul 2013Amber Valley9.0
Warren Housesolar farmsolar farm4refusedupdated Nov 2015Oct 2015refused Jan 2016Nov 2015Ashfield9.6
Park Hall Stud Farmsolar farmsolar farm3.8refusedupdated Jul 2013Nov 2012refused Jul 2013Jul 2013Amber Valley9.6
Heanor Roadbattery storagebattery storage40approved, not builtupdated Mar 2025Feb 2024granted Feb 2025Mar 2025Amber Valley10.0
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alfreton Leisure Centre Car Park, Church Streetrooftop solarrooftop solar0.4approved, not builtupdated Oct 2023Jun 2023granted Sep 2023Oct 2023Amber Valley1.5
A G Parfett & Sons Limited, Cotes Park Industrial Estaterooftop solarrooftop solar0.3approved, not builtupdated Oct 2023Sep 2023granted Sep 2023Oct 2023Bolsover1.7
High View Road, South Normanton Battery Energy Storage Unitbattery storagebattery storage—application withdrawnupdated May 2024Mar 2024—May 2024Bolsover3.1
Eurocell Nickel, High View Roadrooftop solarrooftop solar0.6application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Bolsover3.4
Evans Concrete Products, Pye Bridge Industrial Estaterooftop solarrooftop solar0.3application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Amber Valley3.6
Wharf Road & Beaufit Lane, Pinxton - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Bolsover4.2
Eden Meadows, Stretton Road, Morton Solar PV Panels & Battery Energy Storage Systembattery storagebattery storage—refusedupdated Jun 2025Dec 2023refused May 2025Jun 2025North East Derbyshire4.3
Plymouth Avenue, Pinxtonbattery storagebattery storage0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Bolsover4.4
Brookside Way, Huthwaite Solar Photovoltaicsrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Ashfield4.9
Hallgate Farmbattery storagebattery storage—approved, not builtupdated Jan 2026Aug 2025granted Dec 2025Jan 2026North East Derbyshire6.3
Ripley Leisure Centre, Derby Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Jun 2023granted Sep 2023Oct 2023Amber Valley6.6
Lammas Leisure Centre, Lammas Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025Ashfield7.6
Crabtree Lane, Skegbybattery storagebattery storage—approved, not builtupdated Jul 2025Oct 2024granted Jun 2025Jul 2025Ashfield8.1
Brook Farm, High Streetbattery storagebattery storage—approved, not builtupdated Jan 2024Jul 2023granted Dec 2023Jan 2024Amber Valley8.2
Lamtek Limited, Wolsey Driverooftop solarrooftop solar0.8approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025Ashfield8.6
SC Johnson, Denbyrooftop solarrooftop solar0.6under constructionupdated Jun 2022May 2022granted Sep 2022Jun 2022Amber Valley8.9
Aldercar Infant & Nursery School, Godkin Driverooftop solarrooftop solar0.4approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Amber Valley9.0
Hardwick View Road, Holmewoodrooftop solarrooftop solar0.2approved, not builtupdated Mar 2022Feb 2022granted Jul 2023Mar 2022North East Derbyshire9.5
Mcdonalds, Mansfield Road - Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——Ashfield9.8
Factory Tencate Advanced Composites Limited, Amber Driverooftop solarrooftop solar0.5approved, not built may be out of dateupdated Feb 2023Oct 2022granted Dec 2022Feb 2023Amber Valley9.9
Magnavale Limited - Renewable energy plantbattery storagebattery storage0.1approved, not built may be out of dateupdated Jul 2021May 2021granted Aug 2021Jul 2021North East Derbyshire10.0

Distance from the average position of the DE55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm20215858.9
Rooftop solar162140013.4
Battery storage152901231

MW in pipeline: pending, approved and under-construction capacity.

How Amber Valley decides solar, wind and battery applications

ApplicationsAmber ValleyUK
Decided applications (solar, wind, battery)2010,236
Refused6 (30%)19%
Solar refused6 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Amber Valley

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DE55, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.