Energy Projects Near You

Heanor Road (40 MW battery storage)

Heanor Road is a 40 MW battery storage project in Amber Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 February 2025, not yet built; the record was last updated on 17 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
17 March 2025record last updated
Amber Valleycouncil area

Planning timeline

DateStage
28 February 2024Application submitted
14 February 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
17 March 2025
Operator or applicant
Downing Energy Development Company Limited
Planning authority
Amber Valley
Planning application reference
AVA/2024/0059
Address (REPD)
Ne/O Heanor Road,Heanor
Council area (by location)
Amber Valley
Time to decision
50 weeks
Name in REPD
Heanor Road - Battery Energy Storage System
REPD reference
13472

Who decides

ApplicationsAmber ValleyUK
Decided applications (solar, wind, battery)2010,236
Refused6 (30%)19%
Solar refused6 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Derby Roadsolar farm38application submitted5.5
Iron Works Farmsolar farm5refused5.9
Knob Farmsolar farm5refused6.5
Ladywood Farmsolar farm5refused6.9
Long Lane Solar Farm / Nottingham Brick Workssolar farm17under construction8.0
Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farm16.1application submitted8.1
Solar Farm at Boyah Grange Farm Potato Pit Lane Dale Abbeysolar farm35.2application submitted8.6
Former Langton Colliery Sitesolar farm5.7permission expired9.3
Hall Farm Solar Farmsolar farm50refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0138, -1.3531).