Solar, wind and battery projects near Ilkeston (DE7)
50 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DE7 (Erewash): 9 are waiting for a planning decision, 35 approved but not yet running, 3 operational. The largest live scheme is Southfields Farm, Common Lane (130 MW battery storage, approved on 21 August 2024, not yet built), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DE7
Projects of 1 MW and more (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ladywood Farmsolar farm | solar farm | 5 | refusedupdated Nov 2015 | Sep 2015 | refused Oct 2015 | Nov 2015 | Erewash | 2.4 |
| Pinnacle Storage Park, Dale Abbeysolar farm | solar farm | 1 | under constructionupdated Apr 2022 | Mar 2022 | granted Jul 2022 | Apr 2022 | Erewash | 2.5 |
| Newthorpe Wind Turbinewind turbine | wind turbine | 2.5 | operationalupdated Apr 2014 | Dec 2010 | granted Jul 2011 | Apr 2014 | Broxtowe | 3.3 |
| Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farm | solar farm | 16.1 | application submittedupdated May 2025 | Feb 2025 | — | May 2025 | Broxtowe | 3.9 |
| Solar Farm at Boyah Grange Farm Potato Pit Lane Dale Abbeysolar farm | solar farm | 35.2 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | Erewash | 4.2 |
| Heanor Roadbattery storage | battery storage | 40 | approved, not builtupdated Mar 2025 | Feb 2024 | granted Feb 2025 | Mar 2025 | Amber Valley | 4.9 |
| Southfields Farm, Common Lanebattery storage | battery storage | 130 | approved, not builtupdated Sep 2024 | Nov 2022 | granted Aug 2024 | Sep 2024 | Broxtowe | 7.0 |
| Long Lane Solar Farm / Nottingham Brick Workssolar farm | solar farm | 17 | under constructionupdated Dec 2019 | Jul 2015 | granted Nov 2015 | Dec 2019 | Broxtowe | 7.7 |
| Hl Plastics Extrusions, Flamstead House Hall Roadrooftop solar | rooftop solar | 4.1 | approved, not builtupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | Amber Valley | 8.6 |
| ITP Aero, Harrier Parkrooftop solar | rooftop solar | 1.9 | approved, not builtupdated May 2025 | Nov 2024 | granted Dec 2024 | May 2025 | Ashfield | 8.7 |
| Park Hall Stud Farmsolar farm | solar farm | 3.8 | refusedupdated Jul 2013 | Nov 2012 | refused Jul 2013 | Jul 2013 | Amber Valley | 9.4 |
| Derby Sewage Treatment Workswind farm | wind farm | 5 | operationalupdated Aug 2017 | Oct 2010 | granted Oct 2012 | Aug 2017 | Derby | 9.4 |
| Home Farmsolar farm | solar farm | 1.9 | refusedupdated Nov 2015 | Jul 2015 | refused Oct 2015 | Nov 2015 | Amber Valley | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (37)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Manners Avenuerooftop solar | rooftop solar | 0.6 | operationalupdated Jan 2022 | Jan 2022 | granted Oct 2022 | Jan 2022 | Erewash | 0.4 |
| Old Power House Battery Energy Storage Unitbattery storage | battery storage | — | approved, not built may be out of dateupdated Jul 2023 | Jun 2023 | granted Jul 2023 | Jul 2023 | Erewash | 0.4 |
| Donaldson Timber, Hallam Fields Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Erewash | 3.0 |
| Crompton Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Erewash | 3.1 |
| Moto Hospitality, Trowell Services Area North Solar Farm & Batterybattery storage | battery storage | — | application submittedupdated May 2025 | Feb 2025 | — | May 2025 | Broxtowe | 3.9 |
| William Gregg Vc Leisure Centre, Hands Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2023 | Jun 2023 | — | Jul 2023 | Amber Valley | 4.7 |
| Solvay Composites Derbyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | Apr 2025 | granted May 2025 | Jul 2025 | Amber Valley | 4.7 |
| Composites House, Delves Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | Apr 2025 | granted May 2025 | Jul 2025 | Amber Valley | 4.7 |
| Synesqo, Delves Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | Apr 2025 | granted May 2025 | Jul 2025 | Amber Valley | 4.7 |
| Factory Tencate Advanced Composites Limited, Amber Driverooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Feb 2023 | Oct 2022 | granted Dec 2022 | Feb 2023 | Amber Valley | 4.8 |
| Sainsburys Supermarket, Greens Lanerooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Broxtowe | 5.2 |
| Heanor Gate Spencer Academy, Kirkley Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Amber Valley | 5.2 |
| Aldercar Infant & Nursery School, Godkin Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Amber Valley | 5.8 |
| Brunswood Farm, Locko Roadsolar farm | solar farm | 0.2 | approved, not builtupdated Feb 2024 | Apr 2023 | granted Jan 2024 | Feb 2024 | Erewash | 6.3 |
| Hadden Court, Glaisdale Parkwayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Nottingham | 6.6 |
| Glaisdale Point, Units 10 To 12 - Roof Mounted Solar PV Arrayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Oct 2024 | granted Feb 2025 | Feb 2025 | Nottingham | 6.6 |
| George Spencer Academy, Arthur Mee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Mar 2025 | May 2025 | Broxtowe | 6.9 |
| Brook Farm, High Streetbattery storage | battery storage | — | approved, not builtupdated Jan 2024 | Jul 2023 | granted Dec 2023 | Jan 2024 | Amber Valley | 7.0 |
| Harvey Hadden Sports Village, Wigman Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Jan 2025 | granted Feb 2025 | Feb 2025 | Nottingham | 7.1 |
| Bluecoat Beechdale Academy, Harvey Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Nottingham | 7.5 |
| Blenheim Park Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Dec 2024 | granted Jan 2025 | May 2025 | Ashfield | 7.9 |
| Lees Brook Community School, Morley Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Mar 2026 | Apr 2026 | Derby | 8.1 |
| Watnall Road, Hucknall - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Ashfield | 8.3 |
| Aspect Business Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Nottingham | 8.3 |
| SC Johnson, Denbyrooftop solar | rooftop solar | 0.6 | under constructionupdated Jun 2022 | May 2022 | granted Sep 2022 | Jun 2022 | Amber Valley | 8.5 |
| Ambulance Station, Beechdale Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | Nottingham | 8.8 |
| Smartparc Food Hub, Evolution Way - Plot 8 Roof Mounted PV Solar Panelsrooftop solar | rooftop solar | — | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Derby | 9.0 |
| David Lloyd Tennis And Fitness Club, Aspley Lanerooftop solar | rooftop solar | — | approved, not builtupdated Oct 2025 | Jul 2025 | granted Sep 2025 | Oct 2025 | Nottingham | 9.3 |
| Bulwell Academy, Squires Avenuerooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Nottingham | 9.3 |
| Tamworth Road, Long Eaton - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Apr 2025 | granted Sep 2025 | Sep 2025 | Erewash | 9.5 |
| Madison Court, Derwent Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Nottingham | 9.6 |
| Heart Internet, Beeston Business Parkrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Jan 2025 | Jan 2025 | Broxtowe | 9.8 |
| Wheatcroft Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Apr 2022 | Feb 2022 | Derby | 9.9 |
| St Modwen Park, Andressey Wayrooftop solar | rooftop solar | 0.2 | application submitted | May 2026 | — | — | Derby | 9.9 |
| Balfour Beatty Plant & Fleet Services, Rayneswayrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2022 | Jul 2022 | — | Jul 2022 | Derby | 9.9 |
| Ripley Leisure Centre, Derby Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Jun 2023 | granted Sep 2023 | Oct 2023 | Amber Valley | 9.9 |
| JJ Foodservice, Lilac Groverooftop solar | rooftop solar | 0.4 | application submitted | May 2026 | — | — | Broxtowe | 10.0 |
Distance from the average position of the DE7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 3 | 0 | 3 | 69.5 |
| Rooftop solar | 33 | 5 | 27 | 1 | 0 | 15.3 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 7 | 2 | 5 | 0 | 0 | 170 |
MW in pipeline: pending, approved and under-construction capacity.
How Erewash decides solar, wind and battery applications
Erewash has 8 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DE7, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.