Energy Projects Near You

Long Lane Solar Farm / Nottingham Brick Works (17 MW)

Long Lane Solar Farm / Nottingham Brick Works is a 17 MW solar farm project in Broxtowe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 15 July 2016; the record was last updated on 2 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWsolar farm
under constructionstatus in REPD
2 December 2019record last updated
Broxtowecouncil area

Planning timeline

DateStage
22 July 2015Application submitted
11 November 2015Planning permission granted
15 July 2016Construction started

Project details

Technology
solar farm
Capacity
17 MW
Status (REPD)
under construction
Record last updated
2 December 2019
Operator or applicant
Earthworm/ EW Capital
Planning authority
Broxtowe
Planning application reference
15/00525/FUL
Address (REPD)
Land Off, Long Lane, Watnall, Nottingham
Council area (by location)
Broxtowe
Time to decision
16 weeks
Name in REPD
Long Lane Solar Farm / Nottingham Brick Works
REPD reference
5603

Earlier applications for this site

ApplicationMWSubmittedOutcome
Long Lane Solar Farm 15/00174/FUL1714 March 2015refused 17 June 2015

Who decides

Broxtowe has 6 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Moto Hospitality, Trowell Services Area North Solar Farm & Batterysolar farm16.1application submitted6.6
Heanor Roadbattery storage40approved, not built8.0
Former Langton Colliery Sitesolar farm5.7permission expired9.5
Ladywood Farmsolar farm5refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0167, -1.2334).