Fulwood Grange Farm (5 MW solar farm)

Fulwood Grange Farm is a 5 MW solar farm project in Ashfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 21 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
21 May 2020record last updated
Ashfieldcouncil area

Planning timeline

DateStage
30 July 2015Application submitted
25 November 2015Planning permission granted
25 November 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
21 May 2020
Operator or applicant
Fulwood Grange Solar Farm Limited
Planning authority
Ashfield
Planning application reference
V/2015/0455
Site area
10.0 ha
Address (REPD)
Fulwood Grange Farm, Pinxton Lane, Sutton-In-Ashfield
Council area (by location)
Ashfield
Time to decision
17 weeks
REPD reference
5518

Who decides

ApplicationsAshfieldUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused4 of 1812%
Battery storage refused0 of 116%
Median time from submission to decision15.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Twin Yards Solar Farmsolar farm5operational2.0
Former Langton Colliery Sitesolar farm5.7permission expired2.1
Newton Wood Farmbattery storage49.9approved, not built3.7
Hurst Farm, Mansfield Roadbattery storage99.9approved, not built4.6
Hamilton Road Solar Farmsolar farm7refused4.9
Meadow Lane Solar Farmsolar farm19.6under construction5.3
Ashland Solar Farmsolar farm5permission expired5.4
Two Oaks Quarrysolar farm5permission expired6.5
Hall Farm Solar Farmsolar farm50refused6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1099, -1.2956).