Energy Projects Near You

Renewable energy projects in Ashfield

21 solar, wind or battery projects of 150 kW or more are located in Ashfield (REPD, July 2026 extract): 2 pending, 10 approved but not running, 1 operational and 3 refused. The council refused 4 of 19 decided applications (21%; UK 19%), with a median 16 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects in the council area
2awaiting a decision
10approved, not running
21%of decisions refused

How Ashfield decides

ApplicationsAshfieldUK
Decided applications (solar, wind, battery)1910,236
Refused4 (21%)19%
Solar refused4 of 1812%
Battery storage refused0 of 116%
Median time from submission to decision15.6 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Ashfield

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Hamilton Road Solar Farmsolar farmsolar farm7refusedupdated May 2026Jul 2025refused Mar 2026May 2026
Former Langton Colliery Sitesolar farmsolar farm5.7permission expiredupdated Sep 2019Mar 2016granted Jun 2016Sep 2019
Fulwood Grange Farmsolar farmsolar farm5abandonedupdated May 2020Jul 2015granted Nov 2015May 2020
Ashland Solar Farmsolar farmsolar farm5permission expiredupdated Jul 2020Aug 2015granted Nov 2015Jul 2020
Two Oaks Quarrysolar farmsolar farm5permission expiredupdated Aug 2020Sep 2015granted Oct 2015Aug 2020
Crow Trees Farmsolar farmsolar farm4.7operationalupdated Sep 2018Apr 2014granted Jun 2014Sep 2018
Two Dales Farmsolar farmsolar farm4refusedupdated May 2016Jul 2015refused Mar 2016May 2016
Warren Housesolar farmsolar farm4refusedupdated Nov 2015Oct 2015refused Jan 2016Nov 2015
Two Oaks Quarry, Coxmoor Roadsolar farmsolar farm3.8approved, not builtupdated Feb 2024Nov 2022granted Jan 2024Feb 2024
Sherwood Way Southrooftop solarrooftop solar2.7approved, not built may be out of dateupdated Sep 2021Jun 2021granted Sep 2021Sep 2021
Whiteborough Farmsolar farmsolar farm2.2abandonedupdated Jun 2019Aug 2015granted Feb 2016Jun 2019
ITP Aero, Harrier Parkrooftop solarrooftop solar1.9approved, not builtupdated May 2025Nov 2024granted Dec 2024May 2025
Romo, Oddicroft Lanerooftop solarrooftop solar1approved, not builtupdated May 2024Apr 2024granted May 2024May 2024
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lamtek Limited, Wolsey Driverooftop solarrooftop solar0.8approved, not builtupdated Nov 2025Aug 2025granted Sep 2025Nov 2025
Brookside Way, Huthwaite Solar Photovoltaicsrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024
Watnall Road, Hucknall - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026
Mcdonalds, Mansfield Road - Micro Energy Storagebattery storagebattery storage0.2application submittedMay 2026——
Lammas Leisure Centre, Lammas Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025
Blenheim Park Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Jan 2025May 2025
Hucknall Leisure Centre, Linby Roadrooftop solarrooftop solar—approved, not builtupdated May 2025Aug 2023granted Feb 2025May 2025
Crabtree Lane, Skegbybattery storagebattery storage—approved, not builtupdated Jul 2025Oct 2024granted Jun 2025Jul 2025

Postcode districts in Ashfield

DistrictProjects within 10 kmPendingApprovedOperational
NG15373234
NG17543259

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Ashfield by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.