Energy Projects Near You

Newton Wood Farm (49.9 MW battery storage)

Newton Wood Farm is a 49.9 MW battery storage project in Bolsover, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 October 2020, not yet built; the record was last updated on 25 March 2025. REPD also records that the planning permission expired on 28 October 2023, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
25 March 2025record last updated
Bolsovercouncil area

REPD also records that the planning permission expired on 28 October 2023, so the project may not go ahead in this form.

Planning timeline

DateStage
27 May 2020Application submitted
28 October 2020Planning permission granted
28 October 2023Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
25 March 2025
Operator or applicant
Anesco
Planning authority
Bolsover
Planning application reference
20/00202/FUL
Address (REPD)
Newton Wood Farm, Newtonwood Lane, Newton, Alfreton, Derbyshire
Council area (by location)
Bolsover
Time to decision
22 weeks
REPD reference
7780

Who decides

ApplicationsBolsoverUK
Decided applications (solar, wind, battery)2010,236
Refused4 (20%)19%
Solar refused2 of 1212%
Onshore wind refused2 of 245%
Battery storage refused0 of 616%
Median time from submission to decision12.5 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hurst Farm, Mansfield Roadbattery storage99.9approved, not built0.9
Twin Yards Solar Farmsolar farm5operational2.3
Fulwood Grange Farmsolar farm5abandoned3.7
Averhill Farmsolar farm5operational4.5
Padleywood Farmsolar farm5operational4.5
Eden Meadows, Stretton Road, Morton Solar PV Panels & Battery Energy Storage Systemsolar farm49.9refused4.7
Land North of the Wood at Averill Farmsolar farm5operational5.0
Meadow Lane Solar Farmsolar farm19.6under construction5.0
Former Langton Colliery Sitesolar farm5.7permission expired5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1391, -1.3219).