Calow Green Farm (20 MW battery storage)

Calow Green Farm is a 20 MW battery storage project in North East Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2019; the record was last updated on 31 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
31 March 2023record last updated
North East Derbyshirecouncil area

Planning timeline

DateStage
10 September 2018Application submitted
1 April 2019Construction started
1 October 2019Operational
31 March 2020Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
operational
Record last updated
31 March 2023
Operator or applicant
Arlington Energy (formerly Enso Energy)
Planning authority
North East Derbyshire
Planning application reference
18/01011/FL
Address (REPD)
Calow Green Farm, Calow Green, Calow, Chesterfield, Derbyshire
Council area (by location)
North East Derbyshire
Time to decision
81 weeks
REPD reference
7140

Who decides

ApplicationsNorth East DerbyshireUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Solar refused1 of 1912%
Battery storage refused4 of 1016%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land To The East Of Back Lanesolar farm5operational0.6
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built1.1
Lodge Farm, Calowbattery storage25approved, not built1.4
Lings Farm, Birkin Lanesolar farm9application submitted2.5
Cherry Tree Farmsolar farm5operational2.7
Arkwright Solar Farmsolar farm8operational3.5
Langer Lane Solar Farmsolar farm7.5approved, not built4.7
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagesolar farm31operational4.8
Stockley Hill Solar Farmsolar farm5refused5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2216, -1.3743).