Lodge Farm, Calow (25 MW battery storage)

Lodge Farm, Calow is a 25 MW battery storage project in North East Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 July 2025, not yet built; the record was last updated on 22 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtstatus in REPD
22 August 2025record last updated
North East Derbyshirecouncil area

Planning timeline

DateStage
4 November 2024Application submitted
16 July 2025Planning permission granted
16 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
22 August 2025
Operator or applicant
Enray Power
Planning authority
North East Derbyshire
Planning application reference
24/01034/MFL
Address (REPD)
Lodge Farm, Top Road, Calow, Chesterfield
Council area (by location)
North East Derbyshire
Time to decision
36 weeks
Name in REPD
Lodge Farm, Calow - Battery Energy Storage System
REPD reference
17666

Who decides

ApplicationsNorth East DerbyshireUK
Decided applications (solar, wind, battery)2910,236
Refused5 (17%)19%
Solar refused1 of 1912%
Battery storage refused4 of 1016%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land To The East Of Back Lanesolar farm5operational0.9
Calow Green Farmbattery storage20operational1.4
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built2.1
Cherry Tree Farmsolar farm5operational2.4
Arkwright Solar Farmsolar farm8operational2.6
Lings Farm, Birkin Lanesolar farm9application submitted3.8
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagesolar farm31operational3.9
Langer Lane Solar Farmsolar farm7.5approved, not built5.1
The Brecksolar farm5operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.234, -1.3787).