The Breck (5 MW solar farm)

The Breck is a 5 MW solar farm project in Chesterfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2016; the record was last updated on 18 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 August 2016record last updated
Chesterfieldcouncil area

Planning timeline

DateStage
31 July 2015Application submitted
27 October 2015Planning permission granted
1 February 2016Construction started
17 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Chesterfield
Planning application reference
CHE/15/00460/FUL
Site area
11.4 ha
Address (REPD)
The Breck, Breck Lane, Barrow Hill, Chesterfield
Council area (by location)
Chesterfield
Time to decision
13 weeks
REPD reference
5520

Who decides

ApplicationsChesterfieldUK
Decided applications (solar, wind, battery)1510,236
Refused0 (0%)19%
Solar refused0 of 1212%
Battery storage refused0 of 316%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Chesterfield, Hampshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagesolar farm31operational3.0
Arkwright Solar Farmsolar farm8operational3.8
Land South East of Low Common Farmsolar farm8.3refused3.9
Cherry Tree Farmsolar farm5operational5.1
Lodge Farm, Calowbattery storage25approved, not built5.4
Land To The East Of Back Lanesolar farm5operational6.1
Callywhite Lane Commercial Estatebattery storage18abandoned6.2
Calow Green Farmbattery storage20operational6.7
Hasland Photovoltaic Solar Parksolar farm49.9approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2813, -1.3619).