Energy Projects Near You

Solar, wind and battery projects near Sheffield (S20)

67 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of S20 (Sheffield): 8 are waiting for a planning decision, 40 approved but not yet running, 12 operational. The largest live scheme is Moat Lane, Wickersley (100 MW battery storage, approved on 19 November 2025, not yet built), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

67projects within 10 km
8awaiting a decision
40approved, not running
12operational

Projects within 10 km of S20

Projects of 1 MW and more (29)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
New South Farm, Piper Lane Solar Farmsolar farmsolar farm31.2application submittedupdated Jan 2025Dec 2024—Jan 2025Rotherham4.9
New South Farm, Piper Lane Solar Farmbattery storagebattery storage12application submittedupdated Jan 2025Dec 2024—Jan 2025Rotherham4.9
The Brecksolar farmsolar farm5operationalupdated Aug 2016Jul 2015granted Oct 2015Aug 2016Chesterfield6.0
Advanced Manufacturing Research Centrewind farmwind farm2.6operationalupdated Jul 2009Jan 2007granted Jun 2007Jul 2009Rotherham6.1
Land South East of Low Common Farmsolar farmsolar farm8.3refusedupdated Aug 2016Oct 2015refused Jun 2016Aug 2016Bolsover6.1
Land At Penny Hill Lanesolar farmsolar farm5permission expiredupdated Jun 2020Aug 2015granted Nov 2015Jun 2020Rotherham6.5
Penny Hill Lanewind farmwind farm19.8operationalupdated Aug 2013Jul 2009granted May 2010Aug 2013Rotherham6.5
Brinsworth Road, Brinsworthbattery storagebattery storage40application submittedupdated Sep 2024Sep 2024—Sep 2024Rotherham7.4
Lindrick Way, Barlboroughrooftop solarrooftop solar1.3approved, not builtupdated Mar 2024Feb 2024granted Feb 2024Mar 2024Bolsover7.5
Callywhite Lane Commercial Estatebattery storagebattery storage18abandonedupdated Apr 2020Oct 2017—Apr 2020North East Derbyshire7.6
Loscar Farmwind farmwind farm4.5operationalupdated Jul 2012Nov 2004granted Mar 2008Jul 2012Rotherham8.0
Common Farm Solar Farm & Battery Storagesolar farmsolar farm49approved, not built may be out of dateupdated Nov 2025Aug 2022granted Jun 2023Nov 2025Rotherham8.1
Common Farm Solar Farm & Battery Storagebattery storagebattery storage49approved, not built may be out of dateupdated Nov 2025Aug 2022granted Jun 2023Nov 2025Rotherham8.1
Clipper Logistics, Shepcote Lanerooftop solarrooftop solar1.1approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Sheffield8.4
Land at Oxcroft Stocking Groundsolar farmsolar farm4operationalupdated Apr 2016Jul 2015granted Dec 2015Apr 2016Chesterfield8.5
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagesolar farmsolar farm31operationalupdated Jan 2025Jul 2020granted Apr 2021Jan 2025Chesterfield8.5
Shepcote Lanerooftop solarrooftop solar4.3approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Sheffield9.0
Thurcroft Interchange Energy Parkbattery storagebattery storage50application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham9.2
Thurcroft Interchange Energy Park Solar Farmsolar farmsolar farm49.9application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham9.2
Sytner BMW Sheffield, Brightside Wayrooftop solarrooftop solar1approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Sheffield9.3
Nether Moor Fieldbattery storagebattery storage49.9operationalupdated May 2020Sep 2017granted Dec 2017May 2020Rotherham9.3
Land at Oxcroft Stocking Groundsolar farmsolar farm3operationalupdated Apr 2016Aug 2015granted Dec 2015Apr 2016Bolsover9.3
Oxcroft Solar Farmbattery storagebattery storage1operationalupdated Mar 2019Mar 2016—Mar 2019Bolsover9.3
Green Lane, Thurcroftbattery storagebattery storage85approved, not built may be out of dateupdated May 2023Nov 2022granted May 2023May 2023Rotherham9.4
Arkwright Solar Farmsolar farmsolar farm8operationalupdated Dec 2015Sep 2014granted Feb 2015Dec 2015Chesterfield9.6
Petre Streetbattery storagebattery storage20permission expiredupdated Jun 2020Sep 2016granted Nov 2017Jun 2020Sheffield9.7
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Feb 2024granted Nov 2025Dec 2025Rotherham9.7
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Jul 2023granted Nov 2025Dec 2025Rotherham9.8
Blackburn Meadowsbattery storagebattery storage10operationalupdated Mar 2019Aug 2011—Mar 2019Sheffield10.0
Smaller schemes under 1 MW, mostly rooftop solar (38)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Westthorpe Fields Road, Killamarshbattery storagebattery storage0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023North East Derbyshire3.3
Chesterfield Road, Swallownestbattery storagebattery storage—application submitted may be out of dateupdated Oct 2023Sep 2023—Oct 2023Rotherham3.3
Orgreave Place - Flexible Energy Facilitybattery storagebattery storage—approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026Sheffield4.5
Charnock Hall Primary School, Carter Hall Roadrooftop solarrooftop solar0.2application submittedJun 2026——Sheffield4.5
Advanced Blade Building, Brunel Way Solar Photovoltaicsrooftop solarrooftop solar0.8approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Rotherham6.0
Hard Lane, Kiveton Parkbattery storagebattery storage—application submittedupdated Feb 2025Feb 2025—Feb 2025Rotherham6.2
Bochum Parkwaybattery storagebattery storage—abandonedupdated Feb 2019Sep 2017—Feb 2019Sheffield7.3
Dyche Lane, Batemoorbattery storagebattery storage—refusedupdated Jul 2024Feb 2024refused Jun 2024Jul 2024Sheffield7.6
Jepson And Company, East Bank Roadrooftop solarrooftop solar—refusedupdated Mar 2026Dec 2025refused Jan 2026Mar 2026Sheffield7.9
Darnall Roadbattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Mar 2022granted Aug 2022Mar 2022Sheffield8.2
Vodafone Telephone Exchange, Europa Driverooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Sheffield8.2
William Lee, Callywhite Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024North East Derbyshire8.3
William Lee Limited, Callywhite Lanerooftop solarrooftop solar—approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024North East Derbyshire8.3
Seymour, Link Road - Micro Energy Storage Projectbattery storagebattery storage0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Chesterfield8.4
The Big Yellow Self Storage, Queens Roadrooftop solarrooftop solar0.1approved, not builtupdated Nov 2022Aug 2022granted Nov 2022Nov 2022Sheffield8.5
Inkersall Road, Staveley Solar Photovoltaic Farm And Battery Storagebattery storagebattery storage—operationalupdated Jan 2025Jul 2020granted Apr 2021Jan 2025Chesterfield8.5
Broughton Lanerooftop solarrooftop solar0.3approved, not builtupdated Jan 2022Dec 2021granted Feb 2022Jan 2022Sheffield8.5
The Food Warehouse, Meadowhall Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Sheffield8.8
Creswell Road, Clownebattery storagebattery storage0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Bolsover8.8
Sainsburys, Wreakes Lanerooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026North East Derbyshire8.9
Inkersall Primary Academy, Inkersall Green Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Chesterfield9.0
Heraeus Electro-Nite Uk, Sheffield Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023Chesterfield9.1
Special Melted Products, President Way Worksrooftop solarrooftop solar1approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Sheffield9.2
Old Whittington Wastewater Treatment Works, Station Lanesolar farmsolar farm0.2approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Chesterfield9.2
Special Melted Products, Atlas Worksrooftop solarrooftop solar0.3approved, not builtupdated May 2023Dec 2022granted Apr 2023May 2023Sheffield9.2
Jessops Riverside, Brightside Lanerooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Sheffield9.3
Battery Energy Storage Systembattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Rotherham9.4
Carlton Park Hotel, Moorgate Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Apr 2026granted May 2026Jun 2026Rotherham9.4
Ickles Works, Templeborough Solar Photovoltaicsrooftop solarrooftop solar0.5approved, not builtupdated Sep 2022Aug 2022granted Sep 2022Sep 2022Rotherham9.4
Petre & Carlisle Street East & Petre Streetbattery storagebattery storage—approved, not built may be out of dateupdated May 2023Mar 2023granted May 2023May 2023Sheffield9.5
Advanced alloy services, Nobel Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Rotherham9.5
Hunsley Streetbattery storagebattery storage—approved, not built may be out of dateupdated Mar 2023Sep 2022granted Feb 2023Mar 2023Sheffield9.6
Magna Way, Templeboroughbattery storagebattery storage—approved, not built may be out of dateupdated May 2022Apr 2022granted Jun 2022May 2022Rotherham9.7
Macalloy, Caxton Wayrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Rotherham9.7
Meadowhall Centre, Meadowhall Wayrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Sep 2025granted Oct 2025Nov 2025Sheffield9.7
Moat Barn, Moat Lanesolar farmsolar farm—approved, not builtupdated Jul 2025Apr 2024refused Aug 2024Jul 2025Rotherham9.8
Upwell Streetbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Mar 2022granted Oct 2022Apr 2022Sheffield9.8
Holdsworth Cold Store, Duckmantonrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Chesterfield9.8

Distance from the average position of the S20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm122351130
Rooftop solar251230113.9
Wind farm300300
Battery storage2751441437

MW in pipeline: pending, approved and under-construction capacity.

How Sheffield decides solar, wind and battery applications

ApplicationsSheffieldUK
Decided applications (solar, wind, battery)2910,236
Refused4 (14%)19%
Solar refused3 of 2112%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Sheffield

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near S20, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.