Energy Projects Near You

New South Farm, Piper Lane Solar Farm (31.2 MW)

New South Farm, Piper Lane Solar Farm is a 31.2 MW solar farm project in Rotherham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 24 December 2024, no decision recorded; the record was last updated on 24 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

31.2 MWsolar farm
application submittedstatus in REPD
24 January 2025record last updated
Rotherhamcouncil area

Planning timeline

DateStage
24 December 2024Application submitted

Project details

Technology
solar farm
Capacity
31.2 MW
Status (REPD)
application submitted
Record last updated
24 January 2025
Operator or applicant
Abei Energy Group
Planning authority
Rotherham
Planning application reference
RB2025/0029
Site area
31.0 ha
Address (REPD)
New South Farm, Piper Lane, Aston, Sheffield
Council area (by location)
Rotherham
Name in REPD
New South Farm, Piper Lane - Solar Farm
REPD reference
15653

The scheme also includes 12 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsRotherhamUK
Decided applications (solar, wind, battery)3110,236
Refused2 (6%)19%
Solar refused1 of 1612%
Onshore wind refused0 of 345%
Battery storage refused1 of 1216%
Median time from submission to decision8.9 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Penny Hill Lanesolar farm5permission expired1.7
Penny Hill Lanewind farm19.8operational2.1
Common Farm Solar Farm & Battery Storagesolar farm49approved, not built3.5
Common Farm Solar Farm & Battery Storagebattery storage49approved, not built3.5
Nether Moor Fieldbattery storage49.9operational4.5
Thurcroft Interchange Energy Parkbattery storage50application submitted4.6
Thurcroft Interchange Energy Park Solar Farmsolar farm49.9application submitted4.6
Green Lane, Thurcroftbattery storage85approved, not built4.6
Moat Lane, Wickersleybattery storage100approved, not built5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3649, -1.2991).