Land At Penny Hill Lane (5 MW solar farm)

Land At Penny Hill Lane is a 5 MW solar farm project in Rotherham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 20 November 2020; the record was last updated on 19 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
19 June 2020record last updated
Rotherhamcouncil area

Planning timeline

DateStage
11 August 2015Application submitted
20 November 2015Planning permission granted
20 November 2020Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
19 June 2020
Operator or applicant
Banks Renewables
Planning authority
Rotherham
Planning application reference
RB2015/1084
Site area
11.2 ha
Address (REPD)
Land At, Penny Hill Lane, Ulley, Sheffield
Council area (by location)
Rotherham
Time to decision
14 weeks
REPD reference
5710

Who decides

ApplicationsRotherhamUK
Decided applications (solar, wind, battery)3110,236
Refused2 (6%)19%
Solar refused1 of 1612%
Onshore wind refused0 of 345%
Battery storage refused1 of 1216%
Median time from submission to decision8.9 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penny Hill Lanewind farm19.8operational1.1
New South Farm, Piper Lane Solar Farmsolar farm31.2application submitted1.7
Common Farm Solar Farm & Battery Storagebattery storage49approved, not built2.5
Common Farm Solar Farm & Battery Storagesolar farm49approved, not built2.5
Nether Moor Fieldbattery storage49.9operational2.9
Thurcroft Interchange Energy Park Solar Farmsolar farm49.9application submitted3.0
Thurcroft Interchange Energy Parkbattery storage50application submitted3.0
Green Lane, Thurcroftbattery storage85approved, not built3.0
Moat Lane, Wickersleybattery storage100approved, not built3.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.377, -1.2846).