Energy Projects Near You

Solar, wind and battery projects near Sheffield (S25)

34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of S25 (Rotherham): 9 are waiting for a planning decision, 19 approved but not yet running, 3 operational. The largest live scheme is Moat Lane, Wickersley (100 MW battery storage, approved on 19 November 2025, not yet built), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34projects within 10 km
9awaiting a decision
19approved, not running
3operational

Projects within 10 km of S25

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Common Farm Solar Farm & Battery Storagesolar farmsolar farm49approved, not built may be out of dateupdated Nov 2025Aug 2022granted Jun 2023Nov 2025Rotherham2.2
Common Farm Solar Farm & Battery Storagebattery storagebattery storage49approved, not built may be out of dateupdated Nov 2025Aug 2022granted Jun 2023Nov 2025Rotherham2.2
Land At Penny Hill Lanesolar farmsolar farm5permission expiredupdated Jun 2020Aug 2015granted Nov 2015Jun 2020Rotherham4.7
Nether Moor Fieldbattery storagebattery storage49.9operationalupdated May 2020Sep 2017granted Dec 2017May 2020Rotherham5.2
Green Lane, Thurcroftbattery storagebattery storage85approved, not built may be out of dateupdated May 2023Nov 2022granted May 2023May 2023Rotherham5.4
New South Farm, Piper Lane Solar Farmsolar farmsolar farm31.2application submittedupdated Jan 2025Dec 2024—Jan 2025Rotherham5.5
New South Farm, Piper Lane Solar Farmbattery storagebattery storage12application submittedupdated Jan 2025Dec 2024—Jan 2025Rotherham5.5
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Jul 2023granted Nov 2025Dec 2025Rotherham5.5
Moat Lane, Wickersleybattery storagebattery storage100approved, not builtupdated Dec 2025Feb 2024granted Nov 2025Dec 2025Rotherham5.7
Penny Hill Lanewind farmwind farm19.8operationalupdated Aug 2013Jul 2009granted May 2010Aug 2013Rotherham5.7
Thurcroft Interchange Energy Parkbattery storagebattery storage50application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham5.8
Thurcroft Interchange Energy Park Solar Farmsolar farmsolar farm49.9application submittedupdated Jul 2025Jun 2025—Jul 2025Rotherham5.8
Loscar Farmwind farmwind farm4.5operationalupdated Jul 2012Nov 2004granted Mar 2008Jul 2012Rotherham5.9
Aven Industrial Estatebattery storagebattery storage20permission expiredupdated Jun 2020Jun 2017granted Jun 2018Jun 2020Rotherham7.2
Schutz UK Limited, Claylands Avenuerooftop solarrooftop solar1.7approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Bassetlaw7.3
Premier Grocery Products Limited, Claylands Avenuerooftop solarrooftop solar2.6approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Bassetlaw7.3
Steeley Lane, Steetley Solar Photovoltaic Farmsolar farmsolar farm18.7application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023Bassetlaw8.2
Mere Flats Solar Farmsolar farmsolar farm56approved, not built may be out of dateupdated Feb 2026Aug 2022granted May 2023Feb 2026Doncaster8.3
Mere Flats Solar Farmbattery storagebattery storage16application submitted may be out of dateupdated Feb 2026Aug 2022—Feb 2026Doncaster8.3
Hundred Acre Lane, Carlton In Lindricksolar farmsolar farm34application submittedupdated Sep 2025Jul 2025—Sep 2025Bassetlaw8.4
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Macalloy, Caxton Wayrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Rotherham0.8
Advanced alloy services, Nobel Wayrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Rotherham1.4
Hard Lane, Kiveton Parkbattery storagebattery storage—application submittedupdated Feb 2025Feb 2025—Feb 2025Rotherham4.4
Battery Energy Storage Systembattery storagebattery storage—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Rotherham5.4
Moat Barn, Moat Lanesolar farmsolar farm—approved, not builtupdated Jul 2025Apr 2024refused Aug 2024Jul 2025Rotherham6.0
Robinson Healthcare, Lawn Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025Bassetlaw6.0
Maltby / CLNR EES1battery storagebattery storage0.1decommissionedupdated Oct 2016May 2005—Oct 2016Rotherham6.1
Maltby Sports Centre, Maltbyrooftop solarrooftop solar0.5approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Rotherham6.4
Pearsons Assessment And Testing, Hellaby Ind Estaterooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Rotherham6.9
Aven Industrial Park, Tickhill Roadbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2023Aug 2022granted Sep 2022Feb 2023Rotherham7.2
Chesterfield Road, Swallownestbattery storagebattery storage—application submitted may be out of dateupdated Oct 2023Sep 2023—Oct 2023Rotherham7.4
Albion Close Battery Energy Storage Unitbattery storagebattery storage—approved, not built may be out of dateupdated Sep 2023Jun 2023granted Jun 2023Sep 2023Bassetlaw9.0
Westthorpe Fields Road, Killamarshbattery storagebattery storage0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023North East Derbyshire9.2
Bridge Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Bassetlaw9.5

Distance from the average position of the S25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm84300239
Rooftop solar808005.7
Wind farm200200
Battery storage165810412

MW in pipeline: pending, approved and under-construction capacity.

How Rotherham decides solar, wind and battery applications

ApplicationsRotherhamUK
Decided applications (solar, wind, battery)3110,236
Refused2 (6%)19%
Solar refused1 of 1612%
Onshore wind refused0 of 345%
Battery storage refused1 of 1216%
Median time from submission to decision8.9 weeks17.0 weeks
Appeals lodged / allowed0 / 3—

All projects in Rotherham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near S25, 11 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.