Petre Street (20 MW battery storage)

Petre Street is a 20 MW battery storage project in Sheffield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 4 November 2019; the record was last updated on 25 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
permission expiredstatus in REPD
25 June 2020record last updated
Sheffieldcouncil area

Planning timeline

DateStage
5 September 2016Application submitted
24 November 2017Planning permission granted
4 November 2019Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
permission expired
Record last updated
25 June 2020
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Sheffield
Planning application reference
16/03302/FUL
Address (REPD)
Site Of 350 Petre Street, Sheffield
Council area (by location)
Sheffield
Time to decision
64 weeks
REPD reference
6887

Who decides

ApplicationsSheffieldUK
Decided applications (solar, wind, battery)2910,236
Refused4 (14%)19%
Solar refused3 of 2112%
Onshore wind refused1 of 145%
Battery storage refused0 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackburn Meadowsbattery storage10operational3.7
Brinsworth Road, Brinsworthbattery storage40application submitted4.6
Yarra Industrial Estate, Loicher Lanebattery storage20approved, not built4.9
Whitestone Solar Farmsolar farm750application submitted6.8
Maltby Solar Farmsolar farm20application submitted6.8
Claire Court, Rawmarsh Roadbattery storage40approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4015, -1.4453).