Energy Projects Near You

Eakring Solar Farm (11.9 MW)

Eakring Solar Farm is an 11.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.9 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
9 May 2014Application submitted
8 October 2014Planning permission granted
1 December 2014Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
11.9 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Newark and Sherwood
Planning application reference
14/00839/FULM
Address (REPD)
Land To North Of Eaking Road Eakring Nottinghamshire
Council area (by location)
Newark and Sherwood
Time to decision
22 weeks
REPD reference
2320

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stonish Hill (Bilsthorpe)wind farm10.3operational0.4
Bilsthorpe (Land off Forest Lane)solar farm5operational3.6
Inkersall Grange Farmsolar farm49.9operational4.5
Winkburn Estate Solar Farmsolar farm49.9under construction5.2
Rufford Solar Farmsolar farm5refused6.8
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built8.8
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built8.8
Westwood Farm Solar Parksolar farm5.1operational9.6
Netherfield Lanesolar farm19.7operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1547, -1.014).