Main Street, Kelham Solar Farm & Battery Energy Storage (49.9 MW)

Main Street, Kelham Solar Farm & Battery Energy Storage is a 49.9 MW solar farm project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 December 2025, not yet built; the record was last updated on 4 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
4 March 2025record last updated
Newark and Sherwoodcouncil area

Planning timeline

DateStage
17 October 2023Application submitted
31 January 2025Refused by the planning authority
3 December 2025Appeal allowed
3 December 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
4 March 2025
Operator or applicant
Assured Asset Solar 2 Limited (Peridot Solar)
Planning authority
Newark and Sherwood
Planning application reference
23/01837/FULM
Site area
71.2 ha
Address (REPD)
The W/O Main Street, Kelham, Newark
Council area (by location)
Newark and Sherwood
Time to decision
67 weeks
Name in REPD
Main Street, Kelham - Solar Farm & Battery Energy Storage
REPD reference
11998

The scheme also includes 50 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Staythorpe Road, Averhambattery storage300application submitted1.7
Staythorpe Roadbattery storage360under construction1.7
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built4.3
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built4.4
Foxholes Farm, Bathley Lane Solar Farmsolar farm49.9refused5.0
The Grangesolar farm49.9operational5.0
Great North Road Solar Parksolar farm800application submitted5.5
Hawton Wind Farmwind farm9operational5.5
Tuxford Road Solar Farmsolar farm49.9approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0935, -0.8469).