Energy Projects Near You

Staythorpe Road, Averham (300 MW battery storage)

Staythorpe Road, Averham is a 300 MW battery storage project in Newark and Sherwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 7 March 2023, no decision recorded; the record was last updated on 13 March 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
application submittedmay be out of datestatus in REPD
13 March 2023record last updated
Newark and Sherwoodcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
7 March 2023Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
application submitted
Record last updated
13 March 2023
Operator or applicant
SSE Battery Storage Limited
Planning authority
Newark and Sherwood
Planning application reference
23/00317/FULM
Address (REPD)
Staythorpe Road Averham
Council area (by location)
Newark and Sherwood
Name in REPD
Staythorpe Road, Averham - Battery Storage
REPD reference
12893

Who decides

ApplicationsNewark and SherwoodUK
Decided applications (solar, wind, battery)4110,236
Refused16 (39%)19%
Solar refused8 of 2812%
Onshore wind refused5 of 645%
Battery storage refused3 of 716%
Median time from submission to decision23.4 weeks17.0 weeks
Appeals lodged / allowed8 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Staythorpe Roadbattery storage360under construction<0.1
Main Street, Kelham Solar Farm & Battery Energy Storagesolar farm49.9approved, not built1.7
The Grangesolar farm49.9operational4.3
Hockerton Road, Caunton Solar Farmsolar farm49.9approved, not built4.5
Knapthorpe Grange, Caunton Solar Farmsolar farm49.9approved, not built4.9
Hawton Wind Farmwind farm9operational4.9
Fox Covert Wind Farmwind farm10refused6.0
Foxholes Farm, Bathley Lane Solar Farmsolar farm49.9refused6.5
Great North Road Solar Parksolar farm800application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0813, -0.8628).