Belvoir Estate Solar farm (49.9 MW)

Belvoir Estate Solar farm is a 49.9 MW solar farm project in Melton, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 February 2025, not yet built; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
10 February 2026record last updated
Meltoncouncil area

Planning timeline

DateStage
1 April 2022Application submitted
11 September 2023Refused by the planning authority
7 March 2024Appeal lodged
25 February 2025Appeal allowed
25 February 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
JBM Solar Projects Limited
Planning authority
Melton
Planning application reference
22/00537/FUL
Appeal reference
APP/Y2430/W/24/3340258
Site area
103.5 ha
Address (REPD)
Land To The South West Of Easthorpe Lane Muston
Council area (by location)
Melton
Time to decision
75 weeks
Contracts for Difference
AR7a
Name in REPD
Belvoir Estate - Solar farm
REPD reference
8483

Who decides

ApplicationsMeltonUK
Decided applications (solar, wind, battery)1810,236
Refused2 (11%)19%
Solar refused1 of 1412%
Onshore wind refused1 of 245%
Battery storage refused0 of 216%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jericho Covert Solar Farmsolar farm49.9approved, not built5.1
Sewstern Lane Wind Farmwind farm15refused7.3
Elton solar farmsolar farm5operational7.4
Pastures Farm solar park (Gonerby Lane)solar farm5permission expired8.2
Thackson's Well Wind Farmwind farm23refused8.5
Lodge Farm - Orstonsolar farm12.4operational8.6
Bypass Solar Farmsolar farm50approved, not built9.2
Green Lane & Cliff Lane, Gonerby Moor Solar Farmsolar farm23approved, not built9.2
Grantham Solar Farmsolar farm5operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8947, -0.7827).