Lodge Farm - Orston (12.4 MW solar farm)

Lodge Farm - Orston is a 12.4 MW solar farm project in Rushcliffe, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2014; the record was last updated on 20 May 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.4 MWsolar farm
operationalstatus in REPD
20 May 2014record last updated
Rushcliffecouncil area

Planning timeline

DateStage
16 August 2013Application submitted
15 November 2013Planning permission granted
28 March 2014Operational

Project details

Technology
solar farm
Capacity
12.4 MW
Status (REPD)
operational
Record last updated
20 May 2014
Operator or applicant
Lightsource Renewable Energy
Planning authority
Rushcliffe
Planning application reference
13/01609/FUL
Address (REPD)
Lodge Farm Longhedge Lane Orston Nottinghamshire
Council area (by location)
Rushcliffe
Time to decision
13 weeks
REPD reference
1498

Who decides

ApplicationsRushcliffeUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused4 of 3412%
Battery storage refused3 of 916%
Median time from submission to decision23.1 weeks17.0 weeks
Appeals lodged / allowed2 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Longhedge Solar Farmsolar farm49.9approved, not built2.2
Elton solar farmsolar farm5operational2.2
Sewstern Lane Wind Farmwind farm15refused4.8
Thackson's Well Wind Farmwind farm23refused4.9
Jericho Covert Solar Farmsolar farm49.9approved, not built5.5
Bypass Solar Farmsolar farm50approved, not built6.6
Grantham Solar Farmsolar farm5operational7.4
Fox Covert Wind Farmwind farm10refused7.5
Belvoir Estate Solar farmsolar farm49.9approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.966, -0.8324).